Osama Saad is a Planning and Project Control Consultant, and an experienced online instructor with a demonstrated history of working in super large construction projects. A planner who is passionate about project control. Skilled in planning, sdelay analysis, prolongation costs claims, dispute resolution and cost control. He earned a bachelor degree in Civil Engineering from Cairo University in 2010 then he traveled to England in 2014 to pursue an MBA in which he focused his research in managing construction projects.
He also provided consulting services to one of fortune 500 companies during his studies in England. He has over 11 years of work experience in super large construction projects He is a PMP, PSP and PMI-SP certified.
He launched Smart PM Training (www.smartpmtraining.com) as a platform where professional engineers can learn more about project control. Smart PM Training is a UAE registered company that is accredited and authorized to deliver project management learning.
Planned and earned hours can be tracked. However, you cannot get actual hours by activity. Your subcontractor will only provide total daily hours without breaking them down by activity.
Masha Allah saad, I didn't saw that you have opened a channel on RU-vid for education, amazing bro... i hope u didnt forget ur IT guy in shafar 😛 riyan
Hi Osama!! Thanks for your help with this topic!! Please help me because I have a question. There is a new version of the PMBook guide. In your video you make reference to the 6th edition for relevant chapters. Now 7th edition is available and the contents are not the same. Can we still study base on the 6th edition??
Great video. I have a question, sir. In a Building project that we have 5days duration in STEEL FIXING on each of FLOORS, and the Default Unit/Time I assigned is 8/d in our RESOURCE CREATION. Does it meant that only 8meter road marking is expected to achieve in a day?
Pls, boss, if in a Building project and we have Rebar work to do in each of a the floors for 5days, and the Default Unit/Time is 8/d. Does it meant that only 8TON of Steel fixing is expected to be achieved in a day? Isn't 8Ton that heavy as per weight,
You are the best in this field. I have a question; What if we have like 2 carpenters in a particular project, how many hrs/day are we gonna assign them in Default Unit/Time during resource creation? is it go still remain 10h/d?
Good job Osama .Your lecture is very insightful and helpful. It is a real copilot indeed . Please , the left arrow button to create a sub-category wasn't responding on my dashboard where i have close, add,Delete , Cut , copy , paste, then the four arrows . So what do I do?
Hi. Thank you for you wonderful videos. I have a question bothering me, the question is; How can I put the right activity relationship in the send of MEP rough-in phase work with structural phase work? I have seen so many videos linking MEP rough-in work after completion of structural which I think shouldn't be. Pls correct me, Engr
Scenery: Imagine that we are planning activities that must be finished on a specific date and to do it you must work two shift of 12 hours to work the 24 hours of the day. Question: What would be the set up to apply in the calendar? Should I set up only the time period of 24 hour per day to all the working days or should I do it with the detailed work hour per/day in order to specify the hours of this two shifts to manage better the resources need it?