Softedemy. is a company for project management, training, Planning consultancy services. Softedemy started as a training website back in 2021 and we succeeded to deliver creative learning materials and tools to our planning engineer members on the website. In August 2021, the company was officially launched to expand its website services and to provide creative project management support to construction projects. We are a team of professional planning engineers that can find a solution for every problem. Website : www.softedemy.com
@@SoftEdemy no I am asking about the tool the pen type tool you are using for writing. Is it from the screen recording option? Which screen recorder are you using?
@AhmedMahmoud-es1io product is 100 percent fit . Do no need trail Demos are available to see how it works. Moreover customer support is provided for custom requirements
@zackkhan8506 it's Level of effort activity type when you assign predecessor and successor the duration will be calculated on schedule F9 option. No need to assign duration
When i import excel its adding them as new activities at the bototm of the project instead of updating the udf nect to the original activity...anyone else havung this issue?
@316OceanDaylight if you id in excel and import back then definitely. P6 WILL add them as new activities. This is not issue. It's basic of P6. P6 identify activity uniquness from their IDS. If you want to update the IDs to same activities than UDF column add their first than add new ids their and when you import in P6 update existing project not add new. It's simple method .
@EhabKabani I did the same steps . If mine working and your not working. It's absolutely you are making any mistake in wbs creation. Better to share file to our support for assistance. Info@softedemy.com
You are the best in this field. I have a question; What if we have like 2 carpenters in a particular project, how many hrs/day are we gonna assign them in Default Unit/Time during resource creation? is it go still remain 10h/d?
Great effort putting up this valuable lesson. Thanks so much... Do we need to remove this actual from updated project and reset it to original start date when we wanna make a DELAY ANALYSIS?
Great video..What of in a situation a delay occur in an activity with Total Float of 4 days while the delay lasted for like 10 days, when do I need to report delay evne in this case?
@reginaldibenne6875 if total float is 4 days. And the calendar assigned is 7 days calendar than the delay impact for 10 days will be only 6 days on the schedule . Better to find out other zero float activity which is also relevant and have 10 days delay .otherwise no other option as you cannot create new critical path for baseline programme.
@mahansor8295 advance setting of scheduling F9 . Multiple float than total float last activity. Try to reduce higher float activities. To get maximum Multiple floats
Hii Sir , When we getting approval of baseline from client/ Consulta nt then from this baseline we we prepare recovery plan and adding percentage of each activity and adding actual dates of each activity? Before adding actual dates and percentages we remove the assign baseline?
@toppakistan6129 already mentioned. The video is related to resource allocation using excel. It's not about how to create resource loading sheet. Their are other videos that explain how to create a resource loading sheet. Also please listen clearly what has been explained in the topic title. All the video's are strict to their title names.
Hi. Thank you for you wonderful videos. I have a question bothering me, the question is; How can I put the right activity relationship in the send of MEP rough-in phase work with structural phase work? I have seen so many videos linking MEP rough-in work after completion of structural which I think shouldn't be. Pls correct me, Engr
Please sit with the technical team who will perform the job and ask the sequence of work from them . Whatever they told you arrange the sequence of activities accordingly. Alsl secondly The other way their is MEP work guide Please email to my team at info@softedemy.com and ask for the guide thanks
I have joined as a planning engineer in Gulf for the first time, but I don't have any experience in planning before. By simply doing p6 training course and some theoretical studies,I have successfully got this job , but now I don't have any idea what exactly I have to do. Can you please suggest what I can do since I only know p6. Or atleast tell me specific job activities of a planning engineer in refinery means what work will be given to me. And what work on excel as well. I have still 7-8 days in hand to be shifted to refinery.