Softedemy. is a company for project management, training, Planning consultancy services. Softedemy started as a training website back in 2021 and we succeeded to deliver creative learning materials and tools to our planning engineer members on the website. In August 2021, the company was officially launched to expand its website services and to provide creative project management support to construction projects. We are a team of professional planning engineers that can find a solution for every problem.
Website : www.softedemy.com
Комментарии
@saudpm40
@saudpm40 День назад
Which software are you using for reaching ? It's good also which screen recorder are you using?
@SoftEdemy
@SoftEdemy День назад
@saudpm40 it's excel Microsoft
@saudpm40
@saudpm40 День назад
@@SoftEdemy no I am asking about the tool the pen type tool you are using for writing. Is it from the screen recording option? Which screen recorder are you using?
@SoftEdemy
@SoftEdemy День назад
@@saudpm40 camtesia
@AhmedMahmoud-es1io
@AhmedMahmoud-es1io 8 дней назад
there is no trial version before completing purchasing process ?
@SoftEdemy
@SoftEdemy 8 дней назад
@AhmedMahmoud-es1io product is 100 percent fit . Do no need trail Demos are available to see how it works. Moreover customer support is provided for custom requirements
@arslanch7840
@arslanch7840 10 дней назад
kindly make this project assignment more advanced next level
@SoftEdemy
@SoftEdemy 10 дней назад
@@arslanch7840 sure
@arslanch7840
@arslanch7840 10 дней назад
great information to help me in my career thanks.
@SoftEdemy
@SoftEdemy 10 дней назад
@@arslanch7840 welcome
@remmy5070
@remmy5070 11 дней назад
Thank you for the tips.
@SoftEdemy
@SoftEdemy 11 дней назад
@@remmy5070 welcome
@zackkhan8506
@zackkhan8506 15 дней назад
at 9.02 you said when i schedule it, can you explain that please
@SoftEdemy
@SoftEdemy 15 дней назад
@zackkhan8506 its 5 years back video . What is your question. Just ask exact question
@SoftEdemy
@SoftEdemy 15 дней назад
@zackkhan8506 it's Level of effort activity type when you assign predecessor and successor the duration will be calculated on schedule F9 option. No need to assign duration
@Anand-h1v
@Anand-h1v 15 дней назад
Very expensive brother 😂
@SoftEdemy
@SoftEdemy 15 дней назад
@Anand-h1v 64 metrics. No one schedule comparison do this. With attractive dashboard and summary page
@SoftEdemy
@SoftEdemy 15 дней назад
@@Anand-h1v lifetime updates
@316OceanDaylight
@316OceanDaylight 17 дней назад
When i import excel its adding them as new activities at the bototm of the project instead of updating the udf nect to the original activity...anyone else havung this issue?
@SoftEdemy
@SoftEdemy 17 дней назад
@316OceanDaylight if you id in excel and import back then definitely. P6 WILL add them as new activities. This is not issue. It's basic of P6. P6 identify activity uniquness from their IDS. If you want to update the IDs to same activities than UDF column add their first than add new ids their and when you import in P6 update existing project not add new. It's simple method .
@muhaideen400
@muhaideen400 18 дней назад
Hello sir, How to ignore "No zone" WBS pls explain @12:00
@SoftEdemy
@SoftEdemy 18 дней назад
@@muhaideen400 add dot for no code
@muhaideen400
@muhaideen400 17 дней назад
@@SoftEdemy Thank you sir!
@SoftEdemy
@SoftEdemy 17 дней назад
@@muhaideen400 welcome
@SoftEdemy
@SoftEdemy 16 дней назад
@@muhaideen400 welcome
@EhabKabani
@EhabKabani 18 дней назад
Let me ask you about the topic that my xer not functioning I have followed the same steps
@SoftEdemy
@SoftEdemy 18 дней назад
@EhabKabani I did the same steps . If mine working and your not working. It's absolutely you are making any mistake in wbs creation. Better to share file to our support for assistance. Info@softedemy.com
@EhabKabani
@EhabKabani 18 дней назад
Thank you for all the value information and explanation
@SoftEdemy
@SoftEdemy 16 дней назад
welcome
@EhabKabani
@EhabKabani 18 дней назад
How are you sir
@SoftEdemy
@SoftEdemy 16 дней назад
I am fine
@khajazeeshanuddin5240
@khajazeeshanuddin5240 18 дней назад
U r mental
@zackkhan8506
@zackkhan8506 18 дней назад
I am new in gulf has started career as civil planning engineer . kindly give tips more. thank you for the amazing videos
@SoftEdemy
@SoftEdemy 18 дней назад
@zackkhan8506 watch our videos to learn planning work
@zackkhan8506
@zackkhan8506 17 дней назад
@@SoftEdemy thank you
@SoftEdemy
@SoftEdemy 16 дней назад
@@zackkhan8506 welcome
@zackkhan8506
@zackkhan8506 18 дней назад
thank you sir may Allah give you more for spreading knowledge
@SoftEdemy
@SoftEdemy 18 дней назад
Ameen
@reginaldibenne6875
@reginaldibenne6875 22 дня назад
Awesome! Can we still use this method to create Cashflow S-curve?
@SoftEdemy
@SoftEdemy 22 дня назад
@reginaldibenne6875 cash flow is something else . I Don't have video of it. The graph and calculation is different
@reginaldibenne6875
@reginaldibenne6875 22 дня назад
@@SoftEdemy Okay sir
@mohammadrohail2822
@mohammadrohail2822 23 дня назад
Thank you sir do you have any excel file of productivity?
@SoftEdemy
@SoftEdemy 23 дня назад
@mohammadrohail2822 please listen video complete. I have explained everything. Where is where is the link.
@reginaldibenne6875
@reginaldibenne6875 24 дня назад
You are the best in this field. I have a question; What if we have like 2 carpenters in a particular project, how many hrs/day are we gonna assign them in Default Unit/Time during resource creation? is it go still remain 10h/d?
@SoftEdemy
@SoftEdemy 24 дня назад
@reginaldibenne6875 if one will have 8 then two will have 16 hours a day
@reginaldibenne6875
@reginaldibenne6875 24 дня назад
@@SoftEdemy thanks for swift response
@SoftEdemy
@SoftEdemy 24 дня назад
@@reginaldibenne6875 welcome
@Muhammad-jl7tt
@Muhammad-jl7tt 25 дней назад
Great job my issue was solved after watching your video
@SoftEdemy
@SoftEdemy 25 дней назад
@@Muhammad-jl7tt thanks
@ahmedcharara280
@ahmedcharara280 Месяц назад
thanks
@SoftEdemy
@SoftEdemy Месяц назад
@@ahmedcharara280 welcome
@ricartelaoagan1834
@ricartelaoagan1834 Месяц назад
Thank Brothers for sharing your knowledge. successfully i resolve the issue following your video.
@SoftEdemy
@SoftEdemy Месяц назад
@@ricartelaoagan1834 welcome
@khajazeeshanuddin5240
@khajazeeshanuddin5240 Месяц назад
Super
@SoftEdemy
@SoftEdemy Месяц назад
@@khajazeeshanuddin5240 thanks
@reginaldibenne6875
@reginaldibenne6875 Месяц назад
Great effort putting up this valuable lesson. Thanks so much... Do we need to remove this actual from updated project and reset it to original start date when we wanna make a DELAY ANALYSIS?
@SoftEdemy
@SoftEdemy Месяц назад
@reginaldibenne6875 only collapse as built method like this. Not all method. For more search online about delay analysis techniques
@reginaldibenne6875
@reginaldibenne6875 Месяц назад
@@SoftEdemy Okay, sir. Make a vidoe of Delay Analysis, pls
@SoftEdemy
@SoftEdemy Месяц назад
@@reginaldibenne6875 6 types of delay analysis techniques will be shared when I got some spare time
@reginaldibenne6875
@reginaldibenne6875 Месяц назад
@@SoftEdemy Okay, sir
@amirhamza14
@amirhamza14 Месяц назад
best explained sir.
@SoftEdemy
@SoftEdemy Месяц назад
@@amirhamza14 thanks
@pradeepsingh2853
@pradeepsingh2853 Месяц назад
Sir, While applying global change I am doing Delay = Finish but not getting - in operator, in my system it is only showin & sign
@SoftEdemy
@SoftEdemy Месяц назад
@@pradeepsingh2853 not get your question. Can you explain
@reginaldibenne6875
@reginaldibenne6875 Месяц назад
Great video..What of in a situation a delay occur in an activity with Total Float of 4 days while the delay lasted for like 10 days, when do I need to report delay evne in this case?
@SoftEdemy
@SoftEdemy Месяц назад
@reginaldibenne6875 if total float is 4 days. And the calendar assigned is 7 days calendar than the delay impact for 10 days will be only 6 days on the schedule . Better to find out other zero float activity which is also relevant and have 10 days delay .otherwise no other option as you cannot create new critical path for baseline programme.
@reginaldibenne6875
@reginaldibenne6875 Месяц назад
@@SoftEdemy Oh! Thank you, sir
@maurlord
@maurlord Месяц назад
How come 19260 mhs from budgeted unit if you doesn’t assign resources? (min 7,14). Thanks a lot
@SoftEdemy
@SoftEdemy Месяц назад
@maurlord weight assigned. Then by top down estimation . Approximately total manhour assigned. Try to watch again and again video to understand better
@mohammadmalek323
@mohammadmalek323 Месяц назад
That was great
@SoftEdemy
@SoftEdemy Месяц назад
@@mohammadmalek323 😀
@234saranyacr2
@234saranyacr2 Месяц назад
Can you please explain how can we convert start finish dates into baseline start and finish dates
@SoftEdemy
@SoftEdemy Месяц назад
@@234saranyacr2 use global change. Check video secondary part of global change. Apply that global changes to in progress and completed activities
@muslman8881
@muslman8881 2 месяца назад
thanks)
@mahansor8295
@mahansor8295 2 месяца назад
Thanks , could you please advise on multi critical path .
@SoftEdemy
@SoftEdemy 2 месяца назад
@mahansor8295 advance setting of scheduling F9 . Multiple float than total float last activity. Try to reduce higher float activities. To get maximum Multiple floats
@farooqbashir4111
@farooqbashir4111 2 месяца назад
Very Good, Thank You
@SoftEdemy
@SoftEdemy 2 месяца назад
@@farooqbashir4111 welcome
@taimurhassan3800
@taimurhassan3800 2 месяца назад
Respected sir. Can you please upload a video of Making PMS report .
@SoftEdemy
@SoftEdemy 2 месяца назад
@@taimurhassan3800 ok sure
@aldoflorez906
@aldoflorez906 2 месяца назад
Omg
@SoftEdemy
@SoftEdemy 2 месяца назад
@@aldoflorez906 😀
@ABUBAKAR-ne9yz
@ABUBAKAR-ne9yz 2 месяца назад
Very helpful videos keep it up. Make more videos.
@SoftEdemy
@SoftEdemy 2 месяца назад
@@ABUBAKAR-ne9yz thanks
@vasanthsekaran9450
@vasanthsekaran9450 2 месяца назад
ya but that old xer notepad if its blank what we can do??
@SoftEdemy
@SoftEdemy 2 месяца назад
@@vasanthsekaran9450 it's project is empty. No file exists
@mohd.farhankhan6910
@mohd.farhankhan6910 2 месяца назад
Watching in 2024🎉
@SoftEdemy
@SoftEdemy 2 месяца назад
@@mohd.farhankhan6910 good
@BedarBukhat
@BedarBukhat 2 месяца назад
Hii Sir , When we getting approval of baseline from client/ Consulta nt then from this baseline we we prepare recovery plan and adding percentage of each activity and adding actual dates of each activity? Before adding actual dates and percentages we remove the assign baseline?
@SoftEdemy
@SoftEdemy 2 месяца назад
@@BedarBukhat recovery baseline are prepared on update schedule not baseline schedule
@BedarBukhat
@BedarBukhat 2 месяца назад
@@SoftEdemy we take copy of baseline and then we update the schedule ?
@SoftEdemy
@SoftEdemy 2 месяца назад
@@BedarBukhat no use previous weekly and monthly updated schedule
@BedarBukhat
@BedarBukhat 2 месяца назад
@@SoftEdemy if we don’t have previous updated schedule and if I am doing first time update the schedule then I can do this?
@SoftEdemy
@SoftEdemy 2 месяца назад
@@BedarBukhat yes then you can do this. First update the schedule them recovery schedule
@muslman8881
@muslman8881 2 месяца назад
İ was searching it's cause. Thank you very much)
@SoftEdemy
@SoftEdemy 2 месяца назад
@@muslman8881 welcome
@BedarBukhat
@BedarBukhat 2 месяца назад
Hi sir , We use all these Cases to resolve out of sequence activities in one time?
@SoftEdemy
@SoftEdemy 2 месяца назад
Yes
@BedarBukhat
@BedarBukhat 2 месяца назад
Ok sir thankyou so much 😊
@SoftEdemy
@SoftEdemy 2 месяца назад
@@BedarBukhat welcome
@TahirKhosa
@TahirKhosa 2 месяца назад
When i am importing file, software is being close automatically, what could be the reason?
@SoftEdemy
@SoftEdemy 2 месяца назад
Before closing their should be error name . You can check its name first than share it . Please better to check excel tool video. It has wbs importer
@maazahmad7814
@maazahmad7814 Месяц назад
@@SoftEdemy Hi, Sir I am also facing same issue. When i try to import in P6 it closes automatically without showing any error.
@SoftEdemy
@SoftEdemy Месяц назад
@@maazahmad7814 not faced yet this error. May be be some duplication in wbs short code
@maazahmad7814
@maazahmad7814 Месяц назад
@@SoftEdemy I checked, No duplication but still facing same issue
@SoftEdemy
@SoftEdemy Месяц назад
@maazahmad7814 we use our tool excel lite tool for this purpose www.softedemy.com/shop
@toppakistan6129
@toppakistan6129 2 месяца назад
How did you create Resource Assignment Excel Template?
@SoftEdemy
@SoftEdemy 2 месяца назад
From productivity rates and BOQ check other videos at our channel
@toppakistan6129
@toppakistan6129 2 месяца назад
Thank you Kindly mention columns header in excel. Regards
@SoftEdemy
@SoftEdemy 2 месяца назад
@toppakistan6129 already mentioned. The video is related to resource allocation using excel. It's not about how to create resource loading sheet. Their are other videos that explain how to create a resource loading sheet. Also please listen clearly what has been explained in the topic title. All the video's are strict to their title names.
@BaraRaed
@BaraRaed 2 месяца назад
How do you prepare the excel sheet in colors ?
@SoftEdemy
@SoftEdemy 2 месяца назад
Please check below link video ru-vid.com/video/%D0%B2%D0%B8%D0%B4%D0%B5%D0%BE-uBhP_2jKTJE.htmlsi=wYxt7NP1OxembbyP
@saada.siddiqui4737
@saada.siddiqui4737 2 месяца назад
Very informative. Thanks Usually it happens a lot with non-technical clients.
@SoftEdemy
@SoftEdemy 2 месяца назад
Yes. Alot
@salmantakkar
@salmantakkar 2 месяца назад
Is it for ksa ??
@SoftEdemy
@SoftEdemy 2 месяца назад
For gulf mostly. But for other countries where the contract type us different practices are different
@muslman8881
@muslman8881 2 месяца назад
like)
@SoftEdemy
@SoftEdemy 2 месяца назад
Thanks
@reginaldibenne6875
@reginaldibenne6875 3 месяца назад
Hi. Thank you for you wonderful videos. I have a question bothering me, the question is; How can I put the right activity relationship in the send of MEP rough-in phase work with structural phase work? I have seen so many videos linking MEP rough-in work after completion of structural which I think shouldn't be. Pls correct me, Engr
@SoftEdemy
@SoftEdemy 3 месяца назад
Please sit with the technical team who will perform the job and ask the sequence of work from them . Whatever they told you arrange the sequence of activities accordingly. Alsl secondly The other way their is MEP work guide Please email to my team at info@softedemy.com and ask for the guide thanks
@unknownperson1550
@unknownperson1550 3 месяца назад
I have joined as a planning engineer in Gulf for the first time, but I don't have any experience in planning before. By simply doing p6 training course and some theoretical studies,I have successfully got this job , but now I don't have any idea what exactly I have to do. Can you please suggest what I can do since I only know p6. Or atleast tell me specific job activities of a planning engineer in refinery means what work will be given to me. And what work on excel as well. I have still 7-8 days in hand to be shifted to refinery.
@SoftEdemy
@SoftEdemy 3 месяца назад
Email to our team at info@softedemy.com They will guide you
@unknownperson1550
@unknownperson1550 3 месяца назад
Thank you ​@@SoftEdemy
@NANYANG-ju3su
@NANYANG-ju3su 3 месяца назад
Hi Sir , I 'd like to know how can I get that column named A-new start actual start Date ? It can be set by myself ?
@SoftEdemy
@SoftEdemy 3 месяца назад
User defined field