On Day 3 of our project, significant progress has been made at 1 North. All sand and gravels have been successfully removed, paving the way for the initial shaping of tees and fairway bunkers. Additionally, a bury pit has been established in the rough area, where all organics and gravels from both 1 and 6 North are being laid to rest. Over at 6 North, the green, and 9 North tees, the sod is being expertly stripped away. Furthermore, the installation of mainline irrigation has commenced, currently reaching approximately 30% completion on these two holes.