Shoring Wall (Linearly Changing Wall Dimensions)
Contact for assembly: civil3d.designer1@gmail.com
OPERATIONAL STEPS
A simple road with a 3:2 slope, 5 meters in width, will be drawn along a 100-meter route.
An shoring wall will be constructed on the right side of the road, having the following specifications:
- A fixed height of 2 meters between 0-40 meters.
- A linear increase from 2 meters to 8 meters between 40-70 meters.
- A fixed height of 8 meters between 70-100 meters.
No drainage excavation will be carried out behind the wall between 0-40 meters.
Drainage excavation will be conducted behind the wall between 40-100 meters.
Once the project is drawn, calculations for the shoring wall will be performed, including:
- Wall volume
- Backfill material volume behind the wall
- Wall excavation volume
- Normal excavation/fill volume