Bruce Road Construction Update - June 28, 2024 

City of Chico
Подписаться 110
Просмотров 145
50% 1

Footage from Highway 32 to Skyway along the Bruce Road corridor. Footage begins just south of Highway 32 and continues south to Skyway.
Bridge crews are working on setting the forms and rebar for the north footing of the bridge. Roadway work includes grading median areas and trenching/installing streetlight conduit on the southern end of Bruce Road. Asphalt grindings are also being removed from the roadway just south of Humboldt Road on Bruce Road.