CAVITE-LAGUNA EXPRESSWAY (CALAX) PROJECT
Project Description:
The project is a 44.58 km. four (4)-lane closed-system tolled expressway connecting CAVITEX and SLEX. The project will start from the CAVITEX in Kawit, Cavite and end at the SLEX-Mamplasan Interchange in Biñan, Laguna. The project will have the following subsections:
Project Subsections
Length
(km)
1
Cavitex Connection to Open Canal Interchange
8.68
2
Open Canal Interchange to Governor’s Drive Interchange
9.86
3
Governor’s Drive Interchange to Silang (Aguinaldo) Interchange
8.64
4
Silang (Aguinaldo) Interchange to Silang East Interchange
3.16
5
Silang East Interchange to Sta. Rosa-Tagaytay Interchange
5.14
6
Sta. Rosa-Tagaytay Interchange to Laguna Boulevard Interchange
2.34
7
Laguna Boulevard Interchange to Laguna Technopark Interchange
3.30
8
Laguna Technopark Interchange to Mamplasan Toll Barrier
3.46
PPP Scheme: Build-Transfer-Operate
-Private sector to finance, construct, operate and maintain the entire expressway.
Concession Period: 35 years (including 5 years design and construction)
Start of Concession Period: July 10, 2015 (TCA Signing Date)
Right of Way:
60 meters, except for Laguna Techno Park & Laguna Boulevard (40 meters), and Greenfield Development Corporation (50 meters).
Interchanges:
8 interchanges and 1 toll barrierr
Bridges:
3,575 meters inclusive of 444 meters of viaduct
Project Objectives:
This project aims to:
· Support national development policy and provide efficient transport facilities for the Eco-zones in Cavite and Laguna.
· Reduce traffic congestion particularly in Governor’s Drive, Aguinaldo Highway and Sta. Rosa-Tagaytay Road which are heavily congested.
· Improve competitiveness of Region IV-A/CALABARZON as an investment destination.
Project Benefits:
At the end of construction, the project is expected to:
Reduce travel time from CAVITEX (Kawit) to SLEX (Mamplasan Interchange in Biñan, Laguna) from 2 hours to 35 minutes (70% reduction).
Project Concessionaire:
MPCALA Holdings Inc.
Project Cost:
Activities
Amount (Billion)
Civil Works
P 25.425
Right-of-Way
P 10.201
Independent Consultant (50%)
P 0.112
Total
P 35.738
Project Status:
Right-of-Way Acquisition (ROWA) accomplishment (actual site possession)
Ø Laguna Side : 100.00%
Ø Cavite Side : 66.77%
Subsections 8, 7 and 6 (Sta. Rosa to Mamplasan) were partially opened to traffic on October 30, 2019.
Toll Operation Permit (TOP) was issued last February 7, 2020 for Subsections 8, 7 and 6.
Toll Operation Permit (TOP) was issued last June 18, 2021 for Subsection5