I’m a project manager from the A&E side, so I review/certify these for the owner. But I’m reviewing primarily for payment of work completed. Retainage is governed by the contract. So you’d associate those percentages with work for each line item on the far right column. I’ve also seen contractors put a single line item at the bottom showing % throughout the project, and then 100% at close out.