slab
1. shuttering / decking / levelling
2. Rebar ( IR)
3. MEP ( IR )
4.facade inserts / steel structure inserts
5. Pre pour survey
6. concreting ( here grade is C40/50)
7. curing / strength of concrete
8. IF post tensioning slab then Stressing ( IR)
9.Duct cleaning / Grouting / cutting / patching
10. deshuttering/ back proving/ continuous slab survey