How to calculate Planned Percentage in MS Project 

SMJ-Tech
Подписаться 2,1 тыс.
Просмотров 31 тыс.
50% 1

Опубликовано:

 

26 окт 2024

Поделиться:

Ссылка:

Скачать:

Готовим ссылку...

Добавить в:

Мой плейлист
Посмотреть позже
Комментарии : 69   
@allwinbangera211
@allwinbangera211 2 месяца назад
I need help please - I am new to Ms project latest version. Whenever i update actual start and actual end it automatically updates the start and end date column with similar dates. However i have set baseline start n baseline end. Which helps to track. Now i want to calculate the planned percentage based on baseline start and end date insetead of start and end date column . Can you help please to correct my plan?
@SMJTech2020
@SMJTech2020 Месяц назад
Hi, Thanks for reaching out. Starting off with MS Project has its own learning curve. Updating Actual Start automatically updates the Start columns as internally they are the same for MS Project. The best way is to baseline the project and keep a track of project dates. For the planned percentage, do you have a formula defined? You can send it over to smj.tech2020@gmail.com and I will have it looked into
@allwinbangera211
@allwinbangera211 Месяц назад
@@SMJTech2020 Sorry for delay in response your formula really helped thank you
@bluefishaddicted
@bluefishaddicted 8 месяцев назад
Can you write this formula here in the description as you promissed, please?
@SMJTech2020
@SMJTech2020 8 месяцев назад
Here you go IIf(Now()[Finish],"100",Int(ProjDateDiff([Start],[Current Date]+1,[Project Calendar])/[Duration]*100))) & "%"
@MohammadAhmad-eg5vl
@MohammadAhmad-eg5vl 4 месяца назад
hi iam facing a issue, hope you can help me on that. I have uploaded cost for each of the program line item and also aligned the planned %age. Now i want to multiply the allocated cost to the planned%age to get the planned cost upto the status date.....however, when iam multiplying the "cost column" & "Planned %age" it is showing ERROR (maybe because, cost i sin number format & planned %age is in "text".... can you help me on this.... how can i format my planned %age column into number so that same can be multiplied by allocated cost....!!! any help is highly appreciated. Thanks.
@MahmoudElBayoumi-v5o
@MahmoudElBayoumi-v5o 8 месяцев назад
IIf(Now()[Finish],"100",Int(ProjDateDiff([Start],[Current Date]+1,[Project Calendar])/[Duration]*100))) & "%"
@keanny9531
@keanny9531 Год назад
How can you make this reflect within the gannt chart? More like making this the %complete function
@PkPhatsoane
@PkPhatsoane Год назад
Can you please use status date instead of now, as I want to see planned % of a certain day, eg last week Friday, otherwise your formula only shows you planned % as at the current date (computer date).
@SMJTech2020
@SMJTech2020 Год назад
Hi Peter, Your request is very interesting. I will cover this point in one of my upcoming videos. Thanks
@SMJTech2020
@SMJTech2020 Год назад
Hi Peter, you can check out this new video ru-vid.com/video/%D0%B2%D0%B8%D0%B4%D0%B5%D0%BE-Yuximvqr7lA.html Don't forget to like :)
@mohamedbadie7535
@mohamedbadie7535 10 месяцев назад
It does not work ... Especially if you use multiple Summaries Tasks that contain multiple subtasks with FF or SS relationships.
@SMJTech2020
@SMJTech2020 8 месяцев назад
Hey thanks for your message. I haven't come across this specific criteria. Let me check it out.
@johnsonchelladurai6829
@johnsonchelladurai6829 2 года назад
Why the wbs summary tabs is not showing the planned percentage? FYI, Please click to use the formula in the summary tab also. Then it will appear that location
@SMJTech2020
@SMJTech2020 Год назад
Thanks for sharing
@mzorkea
@mzorkea Год назад
thanks for this!
@chanchair.1452
@chanchair.1452 Год назад
Thank you.
@SMJTech2020
@SMJTech2020 Год назад
You're welcome!
@diegocabrera1666
@diegocabrera1666 Год назад
Man, you just saved me 🎉
@SMJTech2020
@SMJTech2020 Год назад
I'm glad that the video was helpful for you.
@MrAlinz007
@MrAlinz007 2 года назад
Thanks for the short formula, it works fine with me. But it shows more than 💯 % when the activity start earlier than the planned date. How to fix it?
@SMJTech2020
@SMJTech2020 2 года назад
You are welcome . The formula shown in the video is applied as per the current date however you can choose the appropriate Field value while creating the formula and apply an IF condition to check if the value is exceeding 100, then you can still show it as 100. I hope this will help you out. You can send me the formula on smj.tech2020@gmail.com with the dates that you are targeting and I can try to help out as well :)
@ahteshamulhaq3381
@ahteshamulhaq3381 2 года назад
I have a doubt there is resources allocation symbol in right side of activity name .in my pc What is resource over location.can you tell me brief in hindi.as I m not perfect in English language
@SMJTech2020
@SMJTech2020 2 года назад
Resource overallocation ka matlab hai keh aik resource same time duration mein aik se ziyada task perform ker raha hai. Aik wajha aur ho sakti hai keh resource ka overall work 8 hours se ziyada barh raha hai.
@goncaloviegas3644
@goncaloviegas3644 Год назад
Awesome, thank you.
@SMJTech2020
@SMJTech2020 Год назад
You're welcome!
@akinawayele6739
@akinawayele6739 Год назад
Thanks
@SMJTech2020
@SMJTech2020 Год назад
Welcome
@KK-dl1ev
@KK-dl1ev Год назад
So after this part I'm getting stuck. If a task Planned % is 100% and that tasks Actual % is 50% as of today and if that task is going to be further delayed by 5 days and we change the Actual start date the Planned % completion is also getting re-adjusted which should not be the case when you Baseline the project and the Planned % completion column is in sync with Baseline Start and End dates. Pls help
@SMJTech2020
@SMJTech2020 Год назад
Hi there, this is a very interesting scenario. However, if you use the Baseline Start date in percentage calculation in formula, it should provide the desired results. I will show this in one of my upcoming videos
@KK-dl1ev
@KK-dl1ev Год назад
@@SMJTech2020 when do u plan to show. This dosent work for me. Why is my Planned % changing when my baseline dates are already set but when i change the Start and Finish dates, the Pl% is also changing per those dates.
@SMJTech2020
@SMJTech2020 Год назад
Hi, I will be uploading a video related to Baseline Adherence percentage calculation in the coming week. Do stay tuned.
@SMJTech2020
@SMJTech2020 Год назад
ru-vid.com/video/%D0%B2%D0%B8%D0%B4%D0%B5%D0%BE-qlhAepeLz6M.html
@francamcewan9736
@francamcewan9736 2 года назад
Hi, why would I get a syntax error?
@SMJTech2020
@SMJTech2020 2 года назад
Hi there. Usually Syntax error comes up in case a bracket is missing. Can you also share which version of MS Project you are using?
@mzorkea
@mzorkea Год назад
Can someone please explain how the "total" planned percentage is calculated out to be (like the backend formula of it)? is it the average of planned % of individual activities? Please help!
@SMJTech2020
@SMJTech2020 Год назад
You can select Roll up which will start displaying the planed percentage on the summary tasks as well and also on the complete project
@toyexpert4618
@toyexpert4618 5 дней назад
@@SMJTech2020 Hi, I'm still stuck to get the overall planned percentage. i can't click at the roll up box option
@moizsalah4963
@moizsalah4963 Год назад
It's only showing % planned of each activity but what about % planned of overall project.. It should be Project %Planned vs % Complete.( Ex:- Till status date project was planned 60% and actual complete is 25%).
@SMJTech2020
@SMJTech2020 Год назад
Hi Moiz, If you select roll up in the custom formula dialog box, you will start getting planned percentage on summary tasks as well which includes the overall project summary task. Try it out and feel free to comment in case you need more help. I'll try to cover this in one of the upcoming videos
@moizsalah4963
@moizsalah4963 Год назад
@@SMJTech2020 Thank You for coming up with the solution..I really appreciate it!👏 It might be working completely but for me I can't able to select roll up in the custom field. I can select only none or use formula. It's my humble request if you get some time make a short video on this.. 🙏 I would be very Grateful to you.!
@SMJTech2020
@SMJTech2020 Год назад
Hi Moiz, I will try to make a video on this as soon as I can
@SMJTech2020
@SMJTech2020 Год назад
Hi Moiz, You can check out this video, I have briefly shown the selection for summary task calculation as well
@SMJTech2020
@SMJTech2020 Год назад
ru-vid.com/video/%D0%B2%D0%B8%D0%B4%D0%B5%D0%BE-Yuximvqr7lA.html
@sakthikumaran3319
@sakthikumaran3319 8 месяцев назад
how to compare planned percent complete and % of complete-- Means 50% is the planned percent and 40% is the actual % complete-- Then 40/50 % = 80% is the Adherence... How to calculate this
@SMJTech2020
@SMJTech2020 7 месяцев назад
This is a very interesting question and you can add one more custom column to apply this formula and show the adherence.
@ahteshamulhaq3381
@ahteshamulhaq3381 2 года назад
Hi, is planned means 💯% ? Actual means daily that had been done
@SMJTech2020
@SMJTech2020 2 года назад
Planned means how much should have completed as per the defined start and finish dates. Actual means the actual percentage done
@matildakholofelochoeu6810
@matildakholofelochoeu6810 2 года назад
Hi, I am getting a syntax error. Can you send me the formular?
@SMJTech2020
@SMJTech2020 2 года назад
Hi Matilda, Thanks for sending an email as well. I have shared the corrected formula to you on email.
@SMJTech2020
@SMJTech2020 2 года назад
IIf(Now() [Finish],"100", Int(ProjDatDiff([Start],[Current Date]+1)/[Duration]*100))) & "%"
@SMJTech2020
@SMJTech2020 2 года назад
Here's the formula for convenience as well
@matildakholofelochoeu6810
@matildakholofelochoeu6810 2 года назад
Why does it also not indicate percentages on some activities?
@SMJTech2020
@SMJTech2020 2 года назад
Usually it will not show percentage on Summary Tasks.
@LA-wq4ul
@LA-wq4ul Год назад
I am using the formula it is working, but sometime the % Complete is not calculated right if I use the formula for Planed Competition.
@SMJTech2020
@SMJTech2020 7 месяцев назад
Oh ok. Can you share some details on the cases where it is not calculating. May be there're some parameters which it is not able to get information on
@ahmedhussien6170
@ahmedhussien6170 Год назад
thanks
@SMJTech2020
@SMJTech2020 Год назад
Welcome
@mohammedhamza259
@mohammedhamza259 2 года назад
I have problem , could you help me , it was appear to me syntax error in "0" , I sent formula to your email please check , necessary
@SMJTech2020
@SMJTech2020 2 года назад
Thanks. Let me check it out
@SMJTech2020
@SMJTech2020 2 года назад
You were getting a syntax error on zero as it was included as ''0'' (zero with two single quotes before and after it) instead of "0" (Zero with double quotes before and after it) . It can be tricky to catch as they both look the same however , if you paste this in the notepad, single quotes are shown with a slight distance. The same issue was with "%" .
@MukunthanIyer
@MukunthanIyer 11 месяцев назад
Can you please share the formula you've used in the comments please?
@SMJTech2020
@SMJTech2020 7 месяцев назад
Hi, just in case you missed the formula, here it is IIf([Status Date][Finish],"100",Int(ProjDateDiff([Start],[Status Date]+1,[Project Calendar])/[Duration]*100))) & "%"
@jonaswinley1468
@jonaswinley1468 2 года назад
Syntax error in "%"
@SMJTech2020
@SMJTech2020 2 года назад
Can you share the formula you are using? (you can send it on smj.tech2020@gmail.com) Do remember we need to put & before "%" in the formula as it concatenates the % sign
@sumera3647
@sumera3647 2 года назад
Could you please send this formula via sample sheet ?? 😢
@SMJTech2020
@SMJTech2020 2 года назад
Please email your query at smj.tech2020@gmail.com
@ShahinNaseri-so3ux
@ShahinNaseri-so3ux 4 месяца назад
I have more better formula Number1: ProjDateDiff([Baseline Start],[Status Date])/480 Number2: [Baseline Duration]/480 Number3: IIf([Number1]=[Number2],100,IIf(([Number1]0),[Number1]/[Number2]*100,0)))
@SMJTech2020
@SMJTech2020 2 месяца назад
Thanks for suggesting.
Далее
Nightmare | Update 0.31.0 Trailer | Standoff 2
01:14
Просмотров 500 тыс.
How to CORRECTLY status tasks in Microsoft Project
35:38
MS Project 8 - Tracking Task Progress and Variance
22:19