The Archer Western-de Moya joint venture continues to progress on the Signature Bridge project in downtown Miami.
The weekend of July 23-25, 2021, the project team achieved a major milestone with the successful completion of a 33-hour footing pour for the Signature Bridge's center pier. The center pier will be the principle foundation for the bridge's towering arches. In total, the new bridge will feature six arches, with the tallest at 330 feet above ground.
This weekend’s concrete operation included a collection of impressive quantities, including:
• 5,000 cubic yards of 8,000 psi concrete
• 1,700,000 lbs rebar
• 7 chillers
• 6 miles of cooling pipes
• 5 batch plants
• 4 pump trucks
• 3 generators
• 3 frack tanks for chilled water
Archer Western-de Moya worked in partnership with Universal Engineering Sciences, Titan Concrete, Shelby Erectors, EFCO and U.S. American Concrete Pumping to achieve this significant milestone.

Опубликовано:

 

21 окт 2024

Поделиться:

Ссылка:

Скачать:

Готовим ссылку...

Добавить в:

Мой плейлист
Посмотреть позже
Комментарии : 2   
@ChatGPT1111
@ChatGPT1111 2 года назад
Here in Miami, we call this bridge "The Spider"
@diggleda2952
@diggleda2952 3 года назад
Improved choice of music!!! Fitting
Далее
I tricked MrBeast into giving me his channel
00:58
Просмотров 4,6 млн
DIY Pump Solutions
00:18
Просмотров 1,5 млн
1935 Graphene In Concrete
4:57
Просмотров 28 тыс.
Why Buildings Need Foundations
14:51
Просмотров 3,5 млн
Biggest Megaprojects Under Construction in 2024
20:25
21-03 Miami I-95 North (Video 17-11 Remixed)
24:44
Просмотров 100 тыс.
I tricked MrBeast into giving me his channel
00:58
Просмотров 4,6 млн