I have a doubt about specific calendar can you help me? I Set a specific calendar for a task team, but when the program calculates "hours x team cost/hour"), it actually considers the total hours from the standard calendar (8 hours) and it does reflect in a slightly higher total cost for this team overall; Beacuse not all days of week are 8 hours; But only 3 hours at fridays for example. So in this case, is there something else I´m forgeting to set in the program, in order to give me the right results for this resource cost (team)??