Using Takt to drive The Last Planner® System 

Spencer Easton
Подписаться 412
Просмотров 7 тыс.
50% 1

Опубликовано:

 

11 сен 2024

Поделиться:

Ссылка:

Скачать:

Готовим ссылку...

Добавить в:

Мой плейлист
Посмотреть позже
Комментарии : 13   
@damnbuilder1978
@damnbuilder1978 Год назад
Thanks for taking the time to share this awesome information.
@SpencerEastonChannel
@SpencerEastonChannel Год назад
Thank you Isaac, when a team is so hyper successful that the whole company gives them all raises, pays to have folks fly out to come see it and present this to the LCI as a case study for lean applied well in the field it is worth sharing and taking the time to show what they were doing.
@nkyibe1299
@nkyibe1299 7 месяцев назад
Thank you so very much! This video was very helpful to understand Tact Planning and daily construction management.
@omibonilla7085
@omibonilla7085 Год назад
Very well done video ! 👍🏼
@eugeneorlik9534
@eugeneorlik9534 Год назад
Thank you for a great book overview and fundamentals of Lean.
@Aboard_and_Abroad
@Aboard_and_Abroad 7 месяцев назад
this is an awesome video
@joserenevillanuevaolmedo3622
@joserenevillanuevaolmedo3622 6 месяцев назад
Niiiiiiiiiiiiice, really great
@kennettsinclair3106
@kennettsinclair3106 2 года назад
Love your content Spencer. In this case, is the Takt plan then used to substitute the Phase Plan from where tasks are pulled into the Lookahead and Weekly Work Plans?
@SpencerEastonChannel
@SpencerEastonChannel 2 года назад
Yes, they were using this for the lookahead plan too after about half of the project, they would do weekly work planning and set the expected weekly milestone from the takt plan and then the trades would fill in the changes to the standard flow in the spaces (room 456 the fire sprinkler needs to go first and then the duct work). Once they got into a flow they stopped doing so many meetings because it self regulated. Also the meetings changed from 95% of the time talking about when things would happen and 5% on how to make them happen, to after the takt took hold on the project to 95% of the time in the meetings they would talk how to make things happen and 5% on when because everyone knew when things needed to happen.
@arbhittani
@arbhittani 4 месяца назад
only if music was low
@SpencerEastonChannel
@SpencerEastonChannel 4 месяца назад
that is good feedback, I am trying to learn to be a video production guru at the same time, appreciate the feedback in helping me hone my craft.
@robertszczepaniak8553
@robertszczepaniak8553 2 года назад
Where is the place for flexible adjustments of the kanban cards (which is one of the features of the LPS)? Here it looks like carved in stone…
@SpencerEastonChannel
@SpencerEastonChannel 2 года назад
It’s made with wet estate markers because the stickie notes kept falling off outside, so part of lean and continuous improvement they switched to a whiteboard with wet erase markers. Each trade had a different color marker, and since the proof is in the outcome not the initial standard they kept this way. Not enough people improve things, I believe this team was utilizing employee talent and genius. Thank you for your question, hopefully this answers your question.
Далее
How To Do Takt Planning
18:47
Просмотров 8 тыс.
Pull Planning - Lean Construction
30:24
Просмотров 99 тыс.
iPhone 16 для НИЩЕБРОДОВ!
00:51
Просмотров 1,1 млн
Эконом такси в твоем городе 😂
00:59
Pull Plan Meeting Kickoff Video - HOW TO
21:34
Просмотров 4,1 тыс.
The Last Planner
5:56
Просмотров 11 тыс.
What Is Pull Planning In Construction?
18:29
Просмотров 7 тыс.
A DAY (NIGHT) in the LIFE of a NOC ENGINEER!
12:36
Просмотров 1,8 млн
Glenn Ballard - Lean Construction
1:07:24
Просмотров 23 тыс.
Building a 27-Story High-Rise in Dallas, TX
6:58
Просмотров 7 тыс.
Introduction to the Last Planner System
8:40
Просмотров 47 тыс.
An Example of a Pull Plan
20:52
Просмотров 2,9 тыс.