Тёмный

What is Earned Value Management? Example Formulas | EV, PV, SV, CV, AC 

Project Management Academy
Подписаться 1,3 тыс.
Просмотров 31 тыс.
50% 1

Опубликовано:

 

23 окт 2024

Поделиться:

Ссылка:

Скачать:

Готовим ссылку...

Добавить в:

Мой плейлист
Посмотреть позже
Комментарии : 16   
@esmatsahebdil7499
@esmatsahebdil7499 Год назад
I wonder how this great explanation got no comments. It got only 98 likes. Your explanation, visuals, and everything are worth a lot! Keep up the good work.
@westoncorpengineeringindus4506
I almost " hit the bell buton". Great
@kalabhussain
@kalabhussain 11 месяцев назад
Amazing and simple.....cheers man !!!!!!
@eh8092
@eh8092 11 месяцев назад
Excellent tutorial. 🤠
@westoncorpengineeringindus4506
Comprehensive and good explanation
@franmamone
@franmamone Год назад
how did you get 145k for actual cost?
@Basta-Ardo
@Basta-Ardo 17 дней назад
counting the money you spent for each activities you've done at the baseline
@ojokayode8125
@ojokayode8125 11 месяцев назад
How did you get the planned value figure
@siyamthandakleinbooi3537
@siyamthandakleinbooi3537 Год назад
Thank you :)
@engrasgharbadshah9247
@engrasgharbadshah9247 Год назад
Then what is the difference between earned value and actual cost? Here earned value comes out to be 140k $, which is the amount spent so far in project, so it also becomes our actual cost, so did you assume actual value as 145k $? I have figured out this issue in some other numerical as well.
@The_channel_of_channels
@The_channel_of_channels 11 месяцев назад
Earned value equals the value that was created by the projet at a specific point in time as for the actual cost it is what it cost you to get that earned value. In other words, if cost are above the earned value, it means that it cost you more than expected to create that value.
@nimala363
@nimala363 Год назад
How do calculate AC?
@kalendugodfrey4154
@kalendugodfrey4154 12 дней назад
Well explained but did not explain where you got the $ 145k
@esthercortes7280
@esthercortes7280 4 месяца назад
how you calculate the 145
@jawadelkhoury4877
@jawadelkhoury4877 9 месяцев назад
Actual Cost is always given. You do not calculate it.
Далее
Earned Value Analysis: Worked Example
11:45
Просмотров 46 тыс.
Тупой и ещё тупее. (и поддоны)
00:37
Китайка и Пчелке Холодно😂😆
00:21
EAC: What is Estimate at Completion?
9:01
Просмотров 7 тыс.
What is Earned Value Management - EVM? PM in Under 5
5:53
Earned value analysis worked example
10:32
Просмотров 497 тыс.
10 Project Management Terms You Need to Know
13:57
Просмотров 246 тыс.
Тупой и ещё тупее. (и поддоны)
00:37