One of two 125 ton (net weight) transformers being delivered to a brand new substation being built to connect Pen y Cymoedd Wind Farm to the National Grid. Its twin was delivered the week before.
Each transformer was lowered onto a turntable and the girder frame trailer dismantled from around it, before being spun 90 degrees and pushed into position on rollers.
Many thanks to the guys from ABB, ALE and Shield Security for not telling the guy with the video cameras to bugger off :)