Lets Back Up Six Months in this episode of Barndo Life to where it all Began.
Below are totals of The Appalachian Channel Barndominium Project
Date For What Amount
6/9/23 Purchase of Land $27,000.00 3/4 acre lot
6/9/23 Bank Closing Cost $1,195.00
6/12/23 Title Insurance $165.00
6/13/23 Lowes stakes $7.63
6/21/23 Water & Sewer Tap $1,810.00
6/23/23 Temp Power Pole $600.00
6/14/23 Couty Building Permit $11.50
6/16/23 Lowes $32.75
6/15/23 Lowes $29.45
6/16/23 Walmart Solar lights $79.00
6/17/23 Elect. Permit $175.00
6/18/23 State of Tn Building Console $100.00
6/19/23 State of Tn Building Permit $450.00
6/26/23 2x4's for temp pole $20.90
7/3/23 Co-Op Straw $81.94
7/3/23 Co-Op Straw $230.51
7/3/23 Tractor Supply Grass seeds $83.77
7/4/23 Tractor Supply Grass seeds $169.32
7/5/23 Lowe $ 25.08
7/7/23 Sewer Tank, Pump & supplies $5,196.84
7/7/23 Co-Op Straw stake poles $63.79
7/8/23 Tractor SupplyGrass Seed $97.07
7/8/23 Mail Box & Supplies $164.73
7/10/23 Charlie Copper Dirt Work $2,100.00
7/11/23 Randy Baird Gravel $525.00
7/11/23 Randy Baird Gravel $525.00
7/12/23 Lowes $159.51
7/12/23 Smith Hardware RV Plug $42.13
7/13/23 Cord for sewer pump $83.01
7/15/23 Wal-Mart $101.69
7/16/23 underground wire and plug $110.45
7/16/23 Moving Shed $300.00
7/18/23 Charlies Cooper Dirk Work $400.00
7/18/23 Dwight Cruthesfild Survey $135.00
Total as of July 18th 2023 $42,271.07