Footage from Highway 32 to Skyway along the Bruce Road corridor. Footage begins just south of Highway 32 and continues south to Skyway.
Construction crews are working on the installation of irrigation and water sleeves throughout the project. Storm drain pipe is still being installed as well. Some storm drain drainage inlets are being formed for concrete pours while other drainage inlets are being backfilled. The bridge crew is working on setting the final touches to the diversion pipe in the creek before bridge demolition.