Sir, wrt tp payback period - shouldn't the project with lower payback period be selected and not the one with higher? In the video, you've said to select the one with lower payback period.
Of the following, which statement is correct? A. A project manager must use every process identified within the PMBOK on every project B. A project must use every tool and technique as identified within the PMBOK on every project C. A project manager must use the most appropriate processes on every project D. A project manager must agree that he will use the most appropriate tools and techniques on every project