@cluelessjunkie Thanks for the video. So after getting the volume of concrete for the German floor (in this case it was 6.18m3). How do you calculate (water, cement, sand and aggregates) needed for this 6.18 volume concrete.
I'm not sure what you mean by 'allowance for errors' But if it is to not come short of material from use of the method in the video - I will say that if the calculation is done correctly as shown, there should be leftover of material after the job is done(it is an estimation)
@@cluelessjunkie for example....while casting a pillar, its wooden frame gives way and you'll have to redo that same pillar....does the calculations cover for such occasional errors?