Take an aerial tour of Dacy Business Park as of June 18, 2024! Our latest flyover captures the progress on-site, showing all the building pads taking shape. Select fill is complete on 5 of the 13 pads.
Key Points:
Select Fill Importance: Proper grade and moisture content in select fill are crucial for stability. We used soil injection to stabilize the ground, followed by 3 feet of select fill in 12" lifts, each tested to meet geotechnical standards.
Detention Pond: The retaining wall around the pond is 90% complete, and work has started on the outfall.
Subcontractor Meeting: We held a meeting with all key subs (electrical, plumbing, concrete, erectors). 4E Construction, our General Contractor, ensures smooth communication and coordination. All subcontractors are licensed and experienced in similar projects, making them the backbone of this successful project.
Contact Us
For more information about leasing or purchasing industrial condos at Dacy Business Park, please contact our sales team. We look forward to helping you find the perfect space for your business needs.
Email: sam@dacybusinesspark.com
Phone: 512-577-8088
17 июн 2024