Did you miss us? The church is looking beautiful (and stay through the end for our first interior video!) Here are a few things to keep an eye out for:
- Almost all glass is completely installed, including where the rose window will be!
- The gabled roofs (red roofing) are coming along really well.
- The terrazzo flooring is being poured as we speak and will continue for the next 5 weeks.
- Exterior sheathing continues on the bell tower up to the roof level. Roof sheathing to follow.
- The baptistry is taking shape! Curbs and steps were poured this week.
Going forward, these drone updates will include interior shots. Stay tuned!
www.aggiecatholic.org/newchurch