The North Wildwood Beach Replenishment project is moving at an insane pace.
This past weekend we stopped by the job site to grab some seagull footage of the project. So far crews have been able to finish phase 1.
Phase 1 is laying sand from 8th Ave north and wrap around the jetty on 2nd Ave.
Phase 2 is adding sand to the streets South of 8th Ave.
At this rate, crews are pushing out about 100 by 200 feet of sand a day. With the project projected to be done by July 2nd, we could see the rest of the beaches done all the way down to 26th Street.
Let us know what you think!
To Sign up for Our Patreon page click the link below!
/ wildwoodvideoarchive
Subscribe to our channel - bit.ly/2rk23G7
Follow Me on Instagram - bit.ly/2zRv8K7
Purchase your Wildwood Pins - etsy.me/2LZ1oRK
The equipment used in my videos
Main Drone - DJI Mavic Air 2 - amzn.to/3HZ35tm
On-The-Go Drone - DJI Spark - amzn.to/3tHbSuv
DJI Osmo Action 4K - amzn.to/3Mz886W
Camera - iPhone 12 Plus Max - amzn.to/3CqPv0I
Wireless Mic - Rode Microphones Wireless GO - amzn.to/3MxI3oR
DSLR Camera - Canon Intl. Canon EOS 4000D - amzn.to/3Kn2TFK
#Wildwood #WildwoodNewJersey
5 окт 2024