PMP Practice Questions | Situational PMP questions | PMP Exam Prep 2022 

CareerSprints
Подписаться 2,6 тыс.
Просмотров 41 тыс.
50% 1

In this video, we have solved 15 hard PMP situational questions. Understand the PMP exam pattern and check your understanding of the PMP exam concepts using the questions in this video.
The PMP exam has a high percentage of situational questions using which PMI tests your understanding of handling various situations that come up in project management. A score of greater than 70% in most of the mock exams is indicative of good exam preparation.
-------------------------------------------------------------------------------------------------
⭐⭐⭐ Step up your PMP certification prep with this Agile Practice Guide 2021 Course on Udemy: www.udemy.com/course/pmp-agil...
⭐⭐⭐ Get this PMBOK 7th edition course on Udemy [at a discount]: www.udemy.com/course/pmbok-7t...
⭐⭐⭐ Get this Agile and Scrum certification course on Udemy [Free Agile Certification Included]: www.udemy.com/course/agile-an...
-----------------------------------------------------------------------------------------------------
🆓🆓 Register for this free PMP certification training and learn a free PMP Exam Chapter: www.careersprints.com/free-pm...
-----------------------------------------------------------------------------------------------------
🔖🔖 CareerSprints.com offers high-quality PMP certification exam prep courses aligned with the PMP Exam Content Outline (ECO) | Includes 35 PMP contact hours | Get PMP application sample and help with PMP application audit | Free PMP exam simulators: www.careersprints.com/pmp-tra...
-----------------------------------------------------------------------------------------------------
📱Join 'Learn PMP Scrum Kanban' WhatsApp Group: bit.ly/3zAyU8l
🤳Connect with us on Facebook: / careersprints
🛅 Follow us on Linkedin: bit.ly/3yyNKLk
-----------------------------------------------------------------------------------------------
CareerSprints.com offers courses in PMP, Scrum, ITIL, PRINCE2, DevOps, and Kanban. Reach out to us at info@careersprints.com for any course-related queries. Great corporate discounts are available.
#pmpcertification #pmp2022 #agilepracticeguide #pmpagile #pmpexamprep

Опубликовано:

 

1 авг 2024

Поделиться:

Ссылка:

Скачать:

Готовим ссылку...

Добавить в:

Мой плейлист
Посмотреть позже
Комментарии : 59   
@rekhakokkanti8043
@rekhakokkanti8043 8 месяцев назад
Got 12 correct out of 15. Thank you for sharing the knowledge
@saumya320
@saumya320 Год назад
I got 13 correct out of 15, Hope I could clear at my 1st attempt. Have scheduled my test on 27 Aug 22. Good luck for me
@rakeshbali5252
@rakeshbali5252 Год назад
Have you passed PMP brother
@adnanalmalki
@adnanalmalki Год назад
Did u pass 🎉
@mchllmnrd
@mchllmnrd Год назад
Hope you passed ! If not don't give up, try again...
@lpaone01
@lpaone01 2 года назад
Great Job, thank you so much.
@kshitijrathod3969
@kshitijrathod3969 Год назад
Very well explained. Please come up with many more..
@nirvab.1667
@nirvab.1667 7 месяцев назад
LOVE THIS CONTENT!
@semnaresh8339
@semnaresh8339 Год назад
Nice stuff,great explanation.answered 14/15,
@mustaphalogbi1965
@mustaphalogbi1965 Год назад
Thank you
@raphrryzzy6446
@raphrryzzy6446 2 года назад
Thanks for the insightful work, I have passed my PMP
@lpaone01
@lpaone01 2 года назад
Hi Ralph, any advice on not what to study?
@omonukpoma7892
@omonukpoma7892 2 года назад
Excellent content to aid preparation of my PMP next month. Thanks a lot. Yes indeed #!15 was quite tricky but I believe I understood the "Trick" in the question aka related knowledge area......
@careersprints9681
@careersprints9681 2 года назад
Thanks a lot Omon. Glad to know you found the video useful :)
@sargamkapoor1899
@sargamkapoor1899 Год назад
Good quality questions - different from the others. And I like the way you are presenting - quick & fast
@careersprints9681
@careersprints9681 Год назад
Glad you liked it!
@asignul2009
@asignul2009 Год назад
Thank you. The PO delegation question i definitely got wrong lol
@careersprints9681
@careersprints9681 2 года назад
Please note in question #15 there the correct answer is A since the Project Manager would not meet with individual team members but rather consult or talk to stakeholders before suggesting or making changes to the project variables. Option D says individual team members and not stakeholders. A PM must perform an impact assessment/analysis of all changes before incorporating them. Also, changes must always be analyzed for impact on various project variables before a decision is taken on them (this a key PMI mindset or a proper PM mindset). Sincerely, Rohit from CareerSprints.com
@TheBabyget
@TheBabyget 2 года назад
For question 15, the answer should be D as per the explanation.
@prathameshsatankar6417
@prathameshsatankar6417 2 года назад
Hi. But how project team members can decide which aspects of scope are not of value to the customer?
@TheBabyget
@TheBabyget 2 года назад
@@prathameshsatankar6417 In my opinion, the answer is A. But, if you see his explanation at last, the answer goes to D.
@djro2002
@djro2002 2 года назад
@@prathameshsatankar6417 the correct answer is A, please see the 'pinned' explanation above.
@saumya320
@saumya320 Год назад
Answer A will be the correct answer as it will be the first step to evaluation of the impact and the scope for change, after that he will come to an conclusion whether he will remove any scope from the project post consultation with Project Sponsor.
@asignul2009
@asignul2009 Год назад
One really needs to take time, think and evaluate the questions and their implications
@jimnelson2480
@jimnelson2480 Год назад
Hi, thanks for the PMP preparation exercises. NOTE: I suggest that you listen to your provided answer for question 10. You suggest C. is answer, although you indicate C to be correct Answer. in you statement you say C is Wrong. You kind of, miss match answer to statement made.
@careersprints9681
@careersprints9681 Год назад
Hi Jim, Good observation; glad that you caught it; sorry for the confusion. :) I meant Option C is correct whereas the other options are wrong. Option C is the correct answer. That would be the most logical answer choice for the question. Sincerely, Rohit
@lpaone01
@lpaone01 2 года назад
I would strongly disagree with this answer. This impacts so many people who are also stakeholders (other Teams), perhaps they already have the requested time and resources scheduled for something else. A PM should instinctively, have already completed an impact statement. He should work with stakeholders and project teams to discuss whether this is a viable option, and also get buy-in from all who are involved. Hey, I will give them what they want in order to get certified.
@sumitmitra7336
@sumitmitra7336 2 года назад
For Question 15, the option selected and the answer provided are a mismatch. Also for the " stem " or the ending line of questions how is the following different . For instance what is the difference between the 2 questions : How should the project manager RESPOND or what should the project manager DO NEXT ? are both questions same or different as depending on that the mechanism adopted for option selection could vary..
@careersprints9681
@careersprints9681 2 года назад
Hi Sumit, Please see the 'Pinned' response by CareerSprints and my response to 'Jagan Tarigoppula'. You will find the explanation to question #15. Sincerely, Rohit from CareerSprints.com
@mdg72584
@mdg72584 6 месяцев назад
I have been studying, but I still get some questions that I think should be easy wrong. I will come across a similar question, apply the logic given to the other question, and get blindsided when it’s wrong. Example, changes to scope. There are a number of questions where the answer involves issuing change request and the reasoning provided is that a change to scope MUST go through a change request. Then you see questions like the one in the video about the senior company executive who comes by occasionally to give instruction about urgent feature work. One answer is require issuing of change request. The correct answer is meet with the executive and product owner to agree on a workflow. With the executive occasionally coming by, wouldn’t this only fix it this time vs requiring change request for new items fixing it all the time? Also, how do you differentiate when a question is looking through a lens that wants can you pick change request vs other answers?
@mathewadekunle7991
@mathewadekunle7991 Год назад
The answer for question 15 did not match the explanation in any way. However, in accordance to the explanation, the correct answer should be option B. Please revisit question 15 for clarity. Thank you for your time.
@gopalashetty3592
@gopalashetty3592 2 года назад
Differemnce between Agile Aliance and PMI?
@careersprints9681
@careersprints9681 2 года назад
Hi Gopal, PMI is the project management institute, the body that governs PMP certifications and the Agile alliance is another company which promotes agile values, principles and practices globally. The Agile practice guide, one of the recommended books for the PMP exam is written collaboratively by the Agile Alliance and PMI.
@jagantarigoppula7790
@jagantarigoppula7790 2 года назад
Very interesting scenarios built for these questions. The explanation presented on the slide for question 15 did not go in line with the choice selected. Also for evaluating any change request, it should be submitted to change control board, not a senior person.
@careersprints9681
@careersprints9681 2 года назад
Hi Jagan. Thanks for your comment. For question #15, the primary thing to factor in for the explanation is that since the sponsor is requesting the project length to be shortened this is a change request and the PM will need to check with stakeholders if there is a possibility to reduce the scope of the project to deliver within the timelines (reducing project scope does help with delivering the project faster). The correct answer is A because the PM would need to analyze the impact of this schedule change before incorporating the change. Changes must always be analyzed for impact on various project variables before a decision is taken on them. Also, a change control board is a role that can be taken on by anyone who has the authority to approve or reject a change. This could also be a senior person in an organization, think of small organizations where one person might wear many hats. This means a change control board can be one person too, also called a change authority in some organizations. The term doesn't matter as much as having a person or a committee to take decisions on changes. Hope this clarifies your question.
@saumya320
@saumya320 Год назад
@@careersprints9681 Is it D ? But in my view Answer "A" will be the correct answer as it will be the first step to evaluate the impact and the scope for change, after that he will come to an conclusion whether he will remove any scope from the project post consultation with Project Sponsor.
@coutourplusconfidence8302
@coutourplusconfidence8302 2 года назад
I did well. I only missed 1.
@careersprints9681
@careersprints9681 2 года назад
Great job!!
@bmooremoore4460
@bmooremoore4460 2 года назад
Girl congrats !!! I'm nervous ! Were you able to find a job soon after with great pay?
@tesfayeyalew5563
@tesfayeyalew5563 10 месяцев назад
Q4. A) The fact that end users did not complete their training is no more a risk. It is an issue. Updating the risk register could not, therefore, be the best choice.
@careersprints9681
@careersprints9681 10 месяцев назад
The correct answer for the question is A, you will not wait until the next project status meeting to raise a risk, by then it might be too late which makes B wrong. The risk if raised can be mitigated so that it doesn't become an issue later on. Unresolved risks can turn into issues.
@faresar
@faresar Год назад
I got all correct. Is the exam really that easy?
@careersprints9681
@careersprints9681 Год назад
Hello Congratulations on getting all answers correct. Please practice more questions to get more practice prior to the exam.
@faresar
@faresar Год назад
@@careersprints9681 i just passed yesterday. Used your video to practice. Thanks man
@tasha9650
@tasha9650 Год назад
Was the exam easy? I hear it's hard...
@faresar
@faresar Год назад
@@tasha9650 wasnt easy. Just too many questions and little time
@sumitmitra7336
@sumitmitra7336 2 года назад
For Question 13 , the most suitable appears to be Option C . Instead of D. The items from the Prioritized backlog are SELECTED OR PICKED by the TEAM. They are NOT prioritizing the items , they are just "selecting "the items from the prioritized list basis their own bandwidth and team capacity/ resources at that point of time. The Product owner autonomously could be do product grooming/ Refinement / prioritization as per the business needs , but POST THAT selection of the items from that prioritized list ( which technically is called the SPRINT BACKLOG )is at the sole discretion of the development team . Or the product owner decides which items will be picked and which will BE LEFT in the upcoming iteration? Request you to shed some light on this nuance.
@careersprints9681
@careersprints9681 2 года назад
Hi Sumit, The reason why 'C' is wrong is because the option says 'Select prioritized items from the Sprint backlog'. The team would select items from the Product backlog to include in the sprint backlog. Had it been 'Select items from the product backlog' instead of 'sprint backlog', C would be the correct answer. Hence, the correct answer is 'D' because the team can always add items to the product backlog for the product owner to prioritize. Sincerely, Rohit from CareerSprints.com
@sumitmitra7336
@sumitmitra7336 2 года назад
@@careersprints9681 Thanks Rohit... Clear Oversight from my end & consequently i did not see that it was Sprint Backlog & not a product backlog..
@stayreal9140
@stayreal9140 Год назад
I still disagree with Q13. I don’t believe a team member can add to product backlog. Only the product owner can. Option C still seems correct. Since it talks about selecting ‘for’ the sprint backlog
@careersprints9681
@careersprints9681 Год назад
​@@stayreal9140 A Product Backlog is a wish list of what stakeholders want to see in a product/service. It isn't necessary that the Product Owner would choose everything that's put in the backlog to be built. For option C on why it's wrong, kindly read the explanation given at the top and you'll understand why it's wrong. --Rohit from CareerSprints.com
@Relaxingsounds647
@Relaxingsounds647 Год назад
The reason C is wrong is because Product owner does not work on the sprint backlog that's reserved only for the developers. Developers generate the sprint backlog from the already priorized project backlog
@tesfayeyalew5563
@tesfayeyalew5563 10 месяцев назад
For the final Q, the explanation does not match the answer.
@careersprints9681
@careersprints9681 10 месяцев назад
Read the comments please. it has been pointed out which is the correct answer. -- Rohit from CareerSprints.com
@sumitmitra7336
@sumitmitra7336 2 года назад
Shouldnt be the answer for Question 2 be : Performing instead of Norming... Since they are working " COHESIVELY " ... ( Key Word in Performing stage)
@careersprints9681
@careersprints9681 2 года назад
Hi Sumit, For question 2, it is stated in the scenario that the team has just moved from arguments and contradictions to healthier and better ways of communication. Also, the team has recently developed team norms and procedures for working cohesively. They've not been consistently cohesive which is a characteristic of 'performing'. Hence, the answer is 'norming'. Sincerely, Rohit from CareerSprints.com
@sumitmitra7336
@sumitmitra7336 2 года назад
@@careersprints9681 Thank you for providing conceptual clarity on this one
Далее
180 PMP Exam Practice Questions - Updated for 2024
3:02:43
150 CAPM Exam Practice Questions - Updated for 2024
1:59:16
How much should you MEMORIZE for PMP exam?
50:28
Просмотров 12 тыс.
120 PMI-ACP Exam Practice Questions - Updated for 2024
2:05:28