Project Management Scope Creep: 7 Top Tips To Prevent It! 

ProjectManager
Подписаться 404 тыс.
Просмотров 90 тыс.
50% 1

Learn how to prevent scope creep on projects with these 7 top tips.
Try our award-winning PM software for free: www.projectman...
Projectmanager.com Director Jennifer Bridges shows how you can put techniques in place to manage and/or prevent both scope creep AND "scope creeps" (the annoying people on your project who cause the scope creep!).
1) Define the scope before the project starts.
2) Log the changes to the scope.
3) Rebaseline the project schedule.
4) Request additional funding.
5) Watch your team behaviors for signs of project scope creep.
6) Set priorities.
7) Avoid the trap of being asked to do the time-sapping little extras that ultimately lead to scope creep on projects.
If project management scope creep is something you want to stop, why not claim your free 30-day trial of ProjectManager.com and permanently prevent scope creep from ever happening again!
To subscribe to our RU-vid Channel, click here: / projectmanagervideos
To see another video on controlling scope creep, check out:"Controlling Project Scope: Top 5 Project scope Control Tips".
Just click the link below:
• Controlling Project Sc...

Опубликовано:

 

5 окт 2024

Поделиться:

Ссылка:

Скачать:

Готовим ссылку...

Добавить в:

Мой плейлист
Посмотреть позже
Комментарии : 7   
@yousefkortala5836
@yousefkortala5836 11 лет назад
I wish if Dr.Jennifer were my lecturer,because she's an amazing kind of person.
@jazzmiller2690
@jazzmiller2690 2 года назад
This is a huge point and can’t be overstated, I’m currently on a project where scope creep is waisting a huge amount of resources
@lfrobledanoesteban
@lfrobledanoesteban 12 лет назад
Thank you ProjectManager, because your collection of videos is the best on the field.
@lfrobledanoesteban
@lfrobledanoesteban 12 лет назад
I wanted to highlight that, in my experience, the request and approval for a change (here step or tip 2), should be collocated with the Request for funds (here point 4). Why? First, approval of a Change depends upon what it costs, in time, resources & funding. Getting the approval for the change will therefore imply the approval of the funding. This is assuming that the CMB is not only a technical board but a business one and is involved -somehow- in funding. Thanks again for your work!
@Mayaadyby.
@Mayaadyby. 2 года назад
Completed points! Well done!
@proximoto
@proximoto 10 лет назад
Scope Creep = Design by committee. Chop off some heads.
Далее
Project Portfolio Management Defined
6:06
Просмотров 95 тыс.
Project Manager Interview Questions and Answers
18:19
Просмотров 151 тыс.
Mcdonalds cups and ball trick 🤯🥤 #shorts
00:25
Просмотров 484 тыс.
Project Management: How to Manage Team Performance
9:51
The Wasa - a true story of scope creep
8:09
Просмотров 137 тыс.
Scope Creep - Project Management
9:58
Просмотров 244 тыс.
Master These 7 People Skills to Become a GREAT Leader
14:58
Top 10 Terms Project Managers Use
9:21
Просмотров 1,7 млн