SLIPFORM construction - How does slipform works. Setting out and works on 'slide' platform.
In today's video I am showing couple of slipforms from my site. You will see slipform under construction/assembly, slipform ready to slide and I will 'jump' on the highest one to show you concrete works and all interesting things there. I will show you construction of the slipform rig step by step and explain how it works and tell how it's really great idea 😁
JOIN the best engineering community 👍👍👍 SUBSCRIBE NOW!!! 👍👍👍
leave the THUMBS UP!!! Follow the LinkedIn page 😁
LinkedIn: / siteng
/ greg-stepien-7346ab183
Subscribe: ru-vid.com?sub_...
👷‍♀️👷‍♂️ EVERY GOOD CIVIL SITE ENGINEER MUST HAVE - watch the VID 👉 • 10 MUST haves for CIVI... - items I use and recommend 😁
SAFETY BOOTS-choose your size ⬇️⬇️
👉 amzn.to/3NfjUCJ
👉 www.screwfix.com/p/dewalt-pho...
TAPE MEASURE ⬇️⬇️
👉 amzn.to/3xQ3cEf
👉 amzn.to/3xZ9ykM
TAPE HOLDER ⬇️⬇️
👉 amzn.to/3NzLDOV
👉 ffx.co.uk/product/Get/Makita-...
CALCULATOR - sometimes you can also find them in Supermarkets on the help price 😁⬇️⬇️
👉 amzn.to/3u2hHE6
DRAWING FOLDER ⬇️⬇️
👉 amzn.to/3NqYoeA
👉 amzn.to/39OUNZP
NOTEBOOK - get whatever really to take some notes 😁⬇️⬇️
👉 amzn.to/3HQkbLx
PENCIL - 0.7mm - good price, but for this colour 😁⬇️⬇️
👉 amzn.to/3OlvwW3
PENCIL - 2mm ⬇️⬇️
👉 amzn.to/3QHVIff
JOINER'S PENCIL ⬇️⬇️
👉 amzn.to/3xRIaFl
TIPP-EX - these are the best I used ⬇️⬇️
👉 amzn.to/3QNrKGH
PERMANENT MARKERS ⬇️⬇️
👉 amzn.to/3ykpcZv
CHALK LINE ⬇️⬇️
👉 amzn.to/3A0aUOY
👷‍♀️👷‍♂️TRY TO GET THESE ON SITE BEFORE YOU BUY 😁 👇
RETRO TARGETS - Tell your senior engineer, or PM to order these and they will. It’s sometimes the waiting time…⬇️⬇️
👉 amzn.to/3NkSsnh
STRING LINE - These will do. You can always get a one on reel, or with a handle. The thicker the better really, but don’t go crazy of course 😁 ⬇️⬇️
👉 amzn.to/3u08bkB
SURVEY BOOK - They should have these on the site, if not tell them to order 😁 ⬇️⬇️
👉 amzn.to/3HSLGUv
👷‍♀️👷‍♂️FEW EXTRAS I USE TOO 👇
SMALL SPIRIT LEVEL - you can always borrow from a Chippie if needed 😁 ⬇️⬇️
👉 amzn.to/3OEXs79
KNIFE ⬇️⬇️
👉 amzn.to/3HQKUrl
GLASSES - Despite you will get safety glasses, on some sites they’re really low quality and I don’t want to get my sight worse using them. Fortunately it’s a rare situation :)
👉 amzn.to/3nawPeN
👉 amzn.to/3yhMMWM
GLOVES - I got them first on one of the jobs and I use only these from then 😁⬇️⬇️
👉 amzn.to/3bvldjC
0:00 intro
0:28 Slipform rig
1:38 Rebar
2:26 Hydraulic jacks
3:25 Slipform equipment
3:44 top deck
4:35 'wrapping' it up
5:31 rig ready to start
7:26 Topcon EDM
7:46 Slipform access
8:05 Slipform lasers
8:47 Let's go up!
9:15 bottom deck
9:43 main deck
9:55 concrete pour
10:55 top deck
11:25 measuring screen
11:58 openings in the walls
13:32 slab pull-out bars
13:50 slip rig - stages
14:20 join the community!
-IMPORTANT-
Some links in the description may contain one or more affiliate links for items mentioned in my videos - the items I personally use and recommend. You will support my channel if you use these links, as I will get a small commission of the sale. The price is exactly the same without the link, but this way you will help the continuous growth of the channel. Affiliate links are primarily Amazon.
This video is about: civil engineer,civil engineer UK,setting out,setting out in construction,surveying,surveying for construction,surveying UK,civil engineer UK 2021,surveying UK 2021,construction site,setting out UK 2021,site engineer,site engineer UK,how to do setting out,how to read drawings,career in construction,how to survey in construction,how to use a total station,how to use total station UK 2021,slipform,slipform construction,work on sliprorm,slipform engineer
#civilengineering #constructionuk #siteengineer

Опубликовано:

 

24 июл 2024

Поделиться:

Ссылка:

Скачать:

Готовим ссылку...

Добавить в:

Мой плейлист
Посмотреть позже
Комментарии : 106   
@ColexPreston
@ColexPreston 2 года назад
Great video Greg and well explained 👏 👍
@SITENG
@SITENG 2 года назад
Thanks Jamie! Happy you like it!
@jphayes3370
@jphayes3370 2 года назад
Hi greg, keep up the great work. You have helped me understand the basics of the key skills of civil engineering. Keep it up.
@SITENG
@SITENG 2 года назад
Thanks Jp! Happy to help :) Will be uploading the vids ones I sort my YT access. I am on holiday now and have difficulties. Lucky I can comment :)
@bhernonche
@bhernonche 2 года назад
Excellent video! Looking forward to your next video with interview of engineers.
@SITENG
@SITENG 2 года назад
Thanks Bhernonche! I did not 'get them' when I was there, but definitely will try to speak with them, even if on line.
@georgea1116
@georgea1116 Год назад
Great video mate. Loads of information. Cheers
@SITENG
@SITENG Год назад
Thanks 👍
@Chris-ue6yz
@Chris-ue6yz 3 года назад
nice to see greg
@SITENG
@SITENG 3 года назад
Thanks Chris!
@josephhough211
@josephhough211 2 года назад
Greg, how are you guys transferring datum’s up your cores for the slip? I’ve just been using steel tape for the jump form I’m on at the moment, only 7 levels so not massive. But interested to see how you do it for much taller elements. Seen some guys say these use vertical lazers.
@SITENG
@SITENG 2 года назад
Hi Joseph! It's a steel tape too, but also the lasers. Slipforms on the video using the laser and shows the level all the time. I did not the ones with the laser myself, but has to be nice 😁
@surveybook1468
@surveybook1468 2 года назад
Great Video 😀
@SITENG
@SITENG 2 года назад
Thank you Survey Book :)
@isaiahsabljic1219
@isaiahsabljic1219 9 месяцев назад
This video is a huge help. thank you. Just a quick question.. are the jack rods encased into the concrete just like the reinforcement, or no? any help is appreciated :))
@SITENG
@SITENG 9 месяцев назад
Happy to help. Yes, they are 👍
@Onenesofallah
@Onenesofallah 2 года назад
awsum one greg
@SITENG
@SITENG 2 года назад
Thank you! happy you like it😁
@EricHommeric
@EricHommeric 2 года назад
Good vlog , I worked once on the slipforms , not for me , I don’t like heights and tight places :)
@SITENG
@SITENG 2 года назад
Thanks Eric! Yeah slipform is very specific job and not for everyone. I don't like it too, I couldn't work all the time with slipforms.
@kevinkena9081
@kevinkena9081 Год назад
100% perfect video
@SITENG
@SITENG Год назад
Thank you Kevin!
@mdafsara6363
@mdafsara6363 Год назад
Good work sir
@SITENG
@SITENG Год назад
Thanks
@mohammadafsar705
@mohammadafsar705 Год назад
Good work
@SITENG
@SITENG Год назад
Thank you so much 😀
@kylegreenwood3416
@kylegreenwood3416 Год назад
Interesting video! I’ve ridden 50+ slips here in the USA and Canada. Same method, but very different equipment from what you do are using for elevator cores. Who do you rent the slip yokes, jacks, etc from?
@SITENG
@SITENG Год назад
That job the company owns it (JRL Group). They prepare everything off site and assembly is really quick without 'long' carpentry works. How's working in Canada and US ?
@kylegreenwood3416
@kylegreenwood3416 Год назад
@@SITENG we use a company called Scanada for jacking equipment and build wood forms on site. I enjoy working across North America. Lots of great people working together!
@keerthanashaji3441
@keerthanashaji3441 3 года назад
Wow..it’s interesting
@SITENG
@SITENG 3 года назад
Hi Keerthana, happy you like it, hope you will join the site soon 😊
@abitonphiri9833
@abitonphiri9833 2 года назад
Hi Greg, could you please tell me what ( upstands) are.
@SITENG
@SITENG 2 года назад
Hi Abiton! the easiest way I would say it's 'small wall' few hundred mm high eg.150mm. It is used for example to 'hold' the screed and poured to the finish level height. Also used to sit something on top (windows etc) where you need structural concrete - in this case called plinths, plinth wall as well.
@user-gr6wh7lx2q
@user-gr6wh7lx2q 8 месяцев назад
tell me mate how you join the main rebar of the collector beams to the core wall . thank you
@SITENG
@SITENG 8 месяцев назад
no beams on this one, but that would be couplers mate
@user-gr6wh7lx2q
@user-gr6wh7lx2q 8 месяцев назад
@@SITENG and we'll need various main rebar templates or our surveying team will be exhausted to mark those coupler positions . meaning , another lots of sheet . oh shiiit .....
@husseinlakkis4823
@husseinlakkis4823 3 месяца назад
Hello dear, Do you have any video for the construction of mass concrete foundation for thickness of 5 meters and above. If you have please let me know and how could contact you. would be appreciated.
@SITENG
@SITENG 3 месяца назад
Hi! I don't have a video like this and you can contact me on LinkedIn
@kabirg.c.3398
@kabirg.c.3398 Год назад
Can you please send me the name of laser used in her for slip form or link please
@SITENG
@SITENG Год назад
Hi! I don't have it, sorry, you have to dig for it on net 100% you'll find it. If not come back to me :)
@EdytaStepien
@EdytaStepien 3 года назад
Another great video 😊 very interesting 😊👍
@SITENG
@SITENG 3 года назад
Thank you! Cheers Edi!
@kojo8770
@kojo8770 Год назад
Hi Greg , roughly how many cubic metres gets poured daily and is this a 24hr operation ? Thanks
@SITENG
@SITENG Год назад
Can't remember now TBH, but in terms of height is was often ar. 2m - I don't have the walls section area to tell you, but these were small slips. I worked before on Nova slip and couple of weeks on 100BG (the biggest one that time 😁)before I took over the basement. This one wasn't operating 24h, but there are slips like that 😁
@kojo8770
@kojo8770 Год назад
@@SITENG Thank you for answering, great informative videos
@SITENG
@SITENG Год назад
@@kojo8770 Thanks! Happy you like the vids😁
@albertricohermozo442
@albertricohermozo442 Год назад
Hi sir good day can i apply at slipform technician .. thank you
@SITENG
@SITENG Год назад
You have look on LinkedIn for it, or a cv-library etc
@huskodgn
@huskodgn Год назад
👍🥾👍
@SITENG
@SITENG Год назад
Thanks!
@onlinepg4066
@onlinepg4066 2 года назад
How slab reinforcement joined with slip form wall ??
@SITENG
@SITENG 2 года назад
Hi! It's there on the vid. Kwikastip is used (continuity strip/contibar - pull out bars). After the decking is ready this is first job to do - pull out the bars + do the final check if anything is missing as there might be some drill&fix needed. Then pull out bars are spliced with slab rebar. Rebar is connected and the small recess after taking rebar out in the kwikastrip quarantees good connection in terms of shear force.
@onlinepg4066
@onlinepg4066 2 года назад
@@SITENG tq
@SITENG
@SITENG 2 года назад
You're welcome 😁
@elmankhan4571
@elmankhan4571 Год назад
If i have a civil DAE, can i get a job in england
@SITENG
@SITENG Год назад
You will need a work permit in UK, or a sponsorship from a UK company
@funnyvideo7252
@funnyvideo7252 Год назад
sir i have knowledge about slipform and i am a civil engineer so i will get job
@SITENG
@SITENG Год назад
look for it, there are jobs for slipform engineers, so there shouldn't be a problem
@jamieconlan8681
@jamieconlan8681 2 года назад
Have you worked on jump form?
@SITENG
@SITENG 2 года назад
Not much really 😁 A was setting a Meva jumpform in 100BG project and also Peri RCS in Alperton
@unknow-tn8fo
@unknow-tn8fo Год назад
Why did you break up with JRL?
@SITENG
@SITENG Год назад
I might be back soon, who knows 😁
@mdafsara6363
@mdafsara6363 Год назад
I am Foreman sir
@SITENG
@SITENG Год назад
Good, so what do you want to know?
@albertricohermozo442
@albertricohermozo442 Год назад
Good day every one i looking for job slipfoming operator ..
@SITENG
@SITENG Год назад
Anyone can help??
@agimkapidani6178
@agimkapidani6178 6 месяцев назад
Helo my friend
@SITENG
@SITENG 6 месяцев назад
Hello 👍
@agimkapidani6178
@agimkapidani6178 6 месяцев назад
It is me on the video 🤔
@agimkapidani6178
@agimkapidani6178 6 месяцев назад
Minutes 03:34
@mohammadafsar705
@mohammadafsar705 Год назад
I am Foreman
@SITENG
@SITENG Год назад
Good! I am an engineer
@jackullla87
@jackullla87 2 года назад
Pan Jan nie pytal zebys juz zostal ? :D
@SITENG
@SITENG 2 года назад
Ja bede pana Jana pytal czy moge jakies filmiki z jego budow robic :)
@unknow-tn8fo
@unknow-tn8fo Год назад
How to transfer datums?
@SITENG
@SITENG Год назад
Use a line laser
@unknow-tn8fo
@unknow-tn8fo Год назад
@@SITENG on the rebar? But we will loose many millimeters let's say if we have 50 stories
@unknow-tn8fo
@unknow-tn8fo Год назад
@@SITENG i know someone are transferring with the tape measure, but is it accurate?
@SITENG
@SITENG Год назад
on the climbing tube, then whatever you need on the rebar - using electric tape.
@SITENG
@SITENG Год назад
Typically there is a good steel tape inside the core to refer to it. If you mean the tape measure that's the one you'll be using almost all the time as you will be measuring off your datums - marks on the rebar etc. Slipform is a tape measure job and it's well enough. BTW tape measure is our best friend and I have impression people want to measure every simple thing using the EDM - whatever can be checked/measured with the tape should be done with the tape :)
@user-lq9wi9ku6s
@user-lq9wi9ku6s Год назад
design of horizontal slip form????
@SITENG
@SITENG Год назад
?? did I say horizontal?
@user-lq9wi9ku6s
@user-lq9wi9ku6s Год назад
@@SITENG sorry I am just asking if there is any available references for designing horizontal slipform
@SITENG
@SITENG Год назад
I don't think there are horizontal ones. You would just pour the walls and move on ( could be done on some rail system). That's why slipform is a great idea as there are no horizontal elements taking the loads 😁
@user-lq9wi9ku6s
@user-lq9wi9ku6s Год назад
@@SITENG I have been asked to design a horizontal slipform for a concrete tunnel
@SITENG
@SITENG Год назад
@@user-lq9wi9ku6s check Peri solutions, they have some shutters on rails running horizontally. Still it will never work that fast , hope you will find something, or convince them to use maybe precast elements to construct the tunnel
@mohammadafsar705
@mohammadafsar705 Год назад
I want you jobe sir
@SITENG
@SITENG Год назад
Great, look for the job and get it
@parwejalam9456
@parwejalam9456 7 месяцев назад
Any vacancy your company please reply me
@SITENG
@SITENG 7 месяцев назад
not at the minute, sorry
@RajuKumar-wm1ix
@RajuKumar-wm1ix Год назад
Hii
@SITENG
@SITENG Год назад
Hi Raj!
@mohammadafsar705
@mohammadafsar705 Год назад
Please reply me sir
@SITENG
@SITENG Год назад
Hi Mohammad!
@habibullahabbasi2600
@habibullahabbasi2600 2 года назад
contecte with me
@SITENG
@SITENG 2 года назад
Let me know please what you need, or contact me on LinkedIn 😁
@govindvekariya8627
@govindvekariya8627 Год назад
Finishing is not good coming
@SITENG
@SITENG Год назад
what do you mean by that?
@govindvekariya8627
@govindvekariya8627 Год назад
@@SITENG sir i am also slipform technician but wall finishing not coming good
@govindvekariya8627
@govindvekariya8627 Год назад
Sometimes concrete stick on panel so effect on wall finishing
@SITENG
@SITENG Год назад
@@govindvekariya8627 yeah wall finish is not the best, but fortunately it's not that important there
@govindvekariya8627
@govindvekariya8627 Год назад
@@SITENG sir can you give me your email ID so i want to do something convection about slipform
Далее
How to check REBAR. QUALITY in construction.
13:45
Просмотров 19 тыс.
CRANE BASE construction process. CRANE ANCHOR
9:07
Просмотров 9 тыс.
QVZ PREMYER LIGA
00:18
Просмотров 448 тыс.
Новые iPhone 16 и 16 Pro Max
00:42
Просмотров 563 тыс.
Success with Self-Performance: Slip-Form
2:45
Просмотров 16 тыс.
Why Retaining Walls Collapse
12:51
Просмотров 3 млн
CAPPING BEAM construction process
8:51
Просмотров 27 тыс.
Giving an Effective Poster Presentation
11:56
Просмотров 771 тыс.
PILING MAT installation process. CBR test
8:03
Просмотров 12 тыс.
Naval Ravikant explains why you don't need to be CEO
22:32
SENIOR Engineer vs SETTING OUT Engineer
7:18
Просмотров 4,4 тыс.