Can you please help me with the scenario below? Issue/Story comes up when a story of 5 points is 90% done but needs a tiny bit more work in the next sprint. Usually we take that forward to the next sprint and finish it there. But the issue is in the sprint burndown (or epic, release burndowns) it shows that we did no work in the first sprint and over worked in the second sprint. What's the solution? Eg. Story - 5 points and left with 2 points of work. I'll move to next sprint bcz PO said it's high priority. What we need to do for above scenario in next sprint ? Please suggest 🙏
You will have keep the story point, you might velocity will be lower this sprint but when you close that story next sprint and take more work it will even out.