Тёмный

HOUSE BUILDING IN THE PHILIPPINES - EPISODE 29: USING FORM CASING TO THE COLUMN 

Retired and Happy in Philippines
Подписаться 38 тыс.
Просмотров 39 тыс.
50% 1

HOUSE BUILDING IN THE PHILIPPINES - EPISODE 29: USING FORM CASING TO THE COLUMN
Message us:
Facebook: / retiredandhappyinph
Email: retiredandhappyinphilippines@gmail.com

Опубликовано:

 

10 дек 2019

Поделиться:

Ссылка:

Скачать:

Готовим ссылку...

Добавить в:

Мой плейлист
Посмотреть позже
Комментарии : 40   
@Pickle_eaters
@Pickle_eaters 3 года назад
as for the Honeycomb. Make sure that the Concrete Cover is enough for the aggregates to fit. usually 3/4" should be the maximum size for gravel. so cover must be altleast 30mm
@nelsonarizabal3829
@nelsonarizabal3829 4 года назад
Nice work 👍
@jackpiket7643
@jackpiket7643 4 года назад
Keep the colums wet for 4 days to let the concrete hardening on his best. Good job mate
@georgegrimes6917
@georgegrimes6917 4 года назад
Hey there, Just a few points about septic tanks. The water level should be 5cm below the bottom of the inlet pipe. The bottom of the lid needs to be a minimum of 9 inches above the water level. The gray water goes into the second chamber because it contains soap , drain cleaner, and other things that could kill the bacteria in the digester. This is also the same height as the black water inlet to chamber 1. The transfer point needs to be at 1/2 the water depth because sand and metal contaminants sink to the bottom and your little gifts are floating in the top couple inches. If the transfer port is at the top or bottom then undigested stuff goes into the second chamber. I use a transfer port into a third chamber that is basically a holding tank for water to use on landscaping the outlet from the third chamber sets the water level in all three chambers. this outlet or overflow is connected to the leaching field or in the PH the gravel layer under the septic tank floor. With two chamber systems you can eliminate the holding tank chamber if you don't water landscaping and put a six inch PVC pipe vertically cemented through a solid chamber 2 floor. The top of the pipe is cut to set the water depth on both chambers. The 9 inches above the water level is for air exchange in the digester and needs a vent pipe in and an above water level port to chamber two is the air exchange exhaust. These two air pipes need to end at as different height as you can make them for thermal siphoning to circulate the air. The exhaust stack is the tallest. My intuition is that your very deep tank will have significant hydrostatic head to force the overflow into the ground. I have never tested this because I use larger surface areas for oxygen exchange benefits which makes for a shallower tank. If you are doing split aircon the evaporator will work on the back wall but exhausting condenser heat between you and your neighbor will not make him a happy camper. You could put the condenser and compressor well above his roof for heat and noise supression and it would still be out of sight, but harder on maintenance. Possibly a platform with a steel ladder up to the compressor and also as a fire escape for the second floor. I hold the vibrator head flat against the outside of the form for surface finish and down inside to get contact with the rebar. Seems to work that way but there are a lot of variables. george and aurora
@nilobonifacio605
@nilobonifacio605 4 года назад
Lack of vibration on where you showed those anomalies on the concrete. Tell them to go up and down on the vibration instead of angling it.
@taffythegreat1986
@taffythegreat1986 4 года назад
Trouble is you can’t have the concrete to wet. Otherwise it’s to weak. You know when it’s just right when you do the slump test. Still looking good 👍👍👍
@fredjohnson4772
@fredjohnson4772 2 года назад
it looks like chit and worse yet like you mentioned they have weakened the concrete tremendously by adding to much water, leaving the vibrator in one spot, etc, etc, etc... they really are a dum bunch of tradesman
@64Dasani
@64Dasani 4 года назад
Another great video! Thanks
@danilocynepppiloveyoumotas2401
@danilocynepppiloveyoumotas2401 2 года назад
long time no see
@Mike-cp7tw
@Mike-cp7tw 4 года назад
Looks good column blowouts sometimes happens but they will figure it out on a fix , in construction there's always plan changes as you go along best to try and keep them minimal when possible 👍🏼
@retiredandhappyinphilippin3329
@retiredandhappyinphilippin3329 4 года назад
Yeah i know,there is no perfect made
@Pickle_eaters
@Pickle_eaters 3 года назад
Slump Test We don't do that here in the Philippines. Seriously most Worker don't even know what is Slump testis.
@davidknight9396
@davidknight9396 3 года назад
Hello. Trying to find your earlier episode, digging the footings. How deep did you put your columns and tie beams?
@taffythegreat1986
@taffythegreat1986 4 года назад
I didn’t do my columns like that. I thought it would be better to do the block work between the cages. Then shutter around the columns afterwards and pour the concrete. This way the concrete ties in every course of block. It’s coming along anyway 👍👍👍👍
@stephenwilscam9058
@stephenwilscam9058 4 года назад
It seems that the norm of having to re-do work in the PI, has not changed at all. The usual answer from the engineer or forman, was always the same. Minimal. Or "good enough". Hopefully, your project turns out well.
@JohnCharville
@JohnCharville 4 года назад
Tie bars added to columns as they are built is GOOD PRACTICE. See the HANDBOOK ON GOOD BUILDING PRACTICE IN THE PHILIPPINES.
@fredjohnson4772
@fredjohnson4772 2 года назад
sub-standard building from bottom to top
@boilerman1498
@boilerman1498 4 года назад
Yan ang tamang paggawa ng hz , una mga poste muna, malinis at matibay...kaya lang magastos lang talaga...magaling yong nakuha nio contractor , hindi bara bara ang gawa....
@retiredandhappyinphilippin3329
@retiredandhappyinphilippin3329 4 года назад
Im sure magaling ang contractor at yung team na nakuha nya..They do their job clean and they always listen to us
@markkristoffersunwar7617
@markkristoffersunwar7617 4 года назад
Nice crew you have..
@retiredandhappyinphilippin3329
@retiredandhappyinphilippin3329 4 года назад
Thanks
@armanfederigan2751
@armanfederigan2751 4 года назад
i did not see any hole or pipe that will connect the 2 chambers of the septic tank..
@mattvilledatz3196
@mattvilledatz3196 4 года назад
Make deal with reduce contract because of wrong colom
@manuelbartolome6663
@manuelbartolome6663 4 года назад
Coloum box buckle cause by vibrator staying in one location for too long...Rookie mistake..Another pilipino practice that needs to improve are.... too short lapping length of wall dowels...and too few wall dowels...
@bouboutadz9077
@bouboutadz9077 4 года назад
They have the good contractor as what the other commentors are saying. Hahaha
@bouboutadz9077
@bouboutadz9077 4 года назад
Horizontal splice from column is short. Hello falling wall.
@cesarcacayan6916
@cesarcacayan6916 2 года назад
That is not the correctbway of chb wall dowels? Unacceptable in rebar to be rebend the rebar and it does not meet the dowel splice length. There is no floor slab for the septic tank. Where are the electrical conduit. Is there any electrical plans. Get a clamp, and clamped it down. To fix the blow out form..
@taffythegreat1986
@taffythegreat1986 4 года назад
That happened to me with one of the columns. It was so annoying. Are you a southerner ? You sound as you’re from the south. Texas way
@retiredandhappyinphilippin3329
@retiredandhappyinphilippin3329 4 года назад
He is from country town of eastern washington “ellensburg” all about hay and produce but joined military after high school
@stewartmcintosh1073
@stewartmcintosh1073 Год назад
You do not keep the vibrator in the column how to vibrate a column is down to the bottom and up slowly and that's it if you are over vibrate you put all the gravel to the bottom
@Arfabiscuit
@Arfabiscuit 4 года назад
Keep it up buddy .
@nilobonifacio605
@nilobonifacio605 4 года назад
It wasn’t the mix... vibration, that’s what you need.
@fredjohnson4772
@fredjohnson4772 2 года назад
proper vibration..... the knuckleheads decided to correct the problem by leaving the vibrator sit in one spot ? they really are a tupid bunch
@jovenastig8677
@jovenastig8677 4 года назад
Not satisfying to me.
@fredjohnson4772
@fredjohnson4772 2 года назад
terrible workmanship....
Далее
Thai House Build Week 11
19:54
Просмотров 465
меня не было еще год
08:33
Просмотров 2,6 млн
SOLAR INSTALLATION I AIRBNB I LC GUESTHOUSE
13:24
Просмотров 2,4 тыс.
Roofing Ready To Typhoon Inside Concrete Hollow Blocks
12:22
Episode 8 - Tie Beam
1:55
Просмотров 1 тыс.