How To Prepare Interim Payment Application For A Complete Project - Full Project Example 

Cost Engineering Professional
Подписаться 37 тыс.
Просмотров 34 тыс.
50% 1

In this video I explain interim payment application and how to prepare it monthly for a complete project, including how to update the monthly work done and payment application summary for every month in the project. Interim or monthly payment applications for a project are linked via previous, current and total work done and what is previously paid and in this video I highlight exactly how to do that.
The Interim Payment Application format is explained in this video:
• How To Prepare Payment...
You can enroll to our complete Quantity Surveying and Cost Estimation online courses from these below links:
**Cost Estimation Course:
cost-engineeri...
**Procurement Course:
cost-engineeri...
If you would like to see takeoff content similar to our course for free , please visit our RU-vid channel:
/ @cepqs
If you would like to join our Facebook page where we discuss everything related to quantity surveying and cost estimation:
/ costengpro

Опубликовано:

 

6 сен 2024

Поделиться:

Ссылка:

Скачать:

Готовим ссылку...

Добавить в:

Мой плейлист
Посмотреть позже
Комментарии : 116   
@mehariyasilkc1342
@mehariyasilkc1342 2 года назад
Thanks for your effort to share your knowledge.. I have a doubt regarding the recovery of advance payment in IP 05. In IP 04, an Amount of AED 864 is remaining in advance payment. Why is it not deducted in IP 05? Pls explain
@CEPQS
@CEPQS Год назад
Because payment number 5 is the statement at completion. Everything should be paid except for the 5% retention
@saud83mech
@saud83mech Год назад
Thank you bro for all the videos. I want to take your course. Please share your contact no
@CEPQS
@CEPQS Год назад
@@saud83mech thank you 🙏. This course is on RU-vid: ru-vid.com/video/%D0%B2%D0%B8%D0%B4%D0%B5%D0%BE-ZPwkHBAWn6g.html
@isaiahevaofficial4259
@isaiahevaofficial4259 2 месяца назад
@@CEPQS
@schoolfield27
@schoolfield27 8 месяцев назад
Let say: The Contractor money in Hand is 7,565 from adv and he claimed a work done of 13,390 which give a total of 20,955 but the client wants to get back the Retention and Recovery of that work done(13,390 - 1,339 - 1,339 = 10,712). so, the new total will be (7,565 + 10,712 = 18,277) which is the cumulative amount, therefor the client will pay the contractor of (18,277 minus Prev 7,567) = 10,712. (i am not very sure if that how the scenario is, in the 1st payment application) thank you very much Sir for your explanation soon.
@mohamedtawakol4623
@mohamedtawakol4623 5 месяцев назад
i believe recovery for advanced payment deducted twice
@mohamedtawakol4623
@mohamedtawakol4623 5 месяцев назад
twice which makes sense (means 20% as it is uniformed on 5 months)
@jakjak7616
@jakjak7616 Месяц назад
Its right , 10712 is the net amount to certify
@nileeshamadushan2232
@nileeshamadushan2232 10 месяцев назад
I have my VIVA Exam test & the problems i had with the IPA were solved.Thank you very much Sir!
@Devanayagam706
@Devanayagam706 2 года назад
You are a life saver... Thanks brother; pls don't stop thinking its getting lesser views.. whoever views it gets the full clear view.. so pls carry on
@CEPQS
@CEPQS 2 года назад
Thank you brother for your valuable support 🙂. Much appreciated 🙏👍
@mohamedaskar1391
@mohamedaskar1391 Год назад
One of the best teacher i have ever seen in my life. Thank u sir for ur explanation. ❤
@CEPQS
@CEPQS Год назад
Thank you 😊
@birhanemeskelabera2810
@birhanemeskelabera2810 Год назад
Dear Mr. Ahmed, Your sincere explanation about preparation of payment certificate is very outstanding and thank you.
@CEPQS
@CEPQS Год назад
Thank you dear, and wish you all the best 🙏
@georgekimutai1298
@georgekimutai1298 Год назад
hello Sir, this is a great presentation you have been making. but i can see you deducted advance payment recovery twice, thats 1339 twice. I thought the calculation should end at 10712
@mzulkifly1
@mzulkifly1 11 дней назад
Same Problem for me Also 🤔
@evansaddo7431
@evansaddo7431 2 года назад
I am really learning . I intend to encourage all my team members to buy the course
@CEPQS
@CEPQS 2 года назад
Thank you Evans 🙏. That is very kind of you ❤️
@Shuhaib_007
@Shuhaib_007 10 месяцев назад
Very good and clear teaching. I like your teaching and explanation. I am worried about my monthly payment certificate. Nobody helps in my office because of those busy moments. Thank you very much for your video and kind heart. Jazakkallah brother. May God protect you and your family and provide you HIS reward agirah.
@nihalahmed7046
@nihalahmed7046 Год назад
Dear Mr Ahmed, your videos very useful to us. Just keep doing these things. May Almighty bless you and your family
@CEPQS
@CEPQS Год назад
Thanks a lot for your kind support and wish you all the best always inshallah 🙏
@eyoabadane8384
@eyoabadane8384 2 года назад
Dear Ahmed can you explain abt the price escalation and price variation by using your payment in detail manner like this video pls
@lathankhalith2110
@lathankhalith2110 4 месяца назад
Dear Adhil, This is very useful presentation to my work and why you not consider a vat in the interim payment.
@mdtouseef6940
@mdtouseef6940 2 года назад
Great video sir, Can you also explain the method and a good invoice format on how to claim / include the following in Interim Invoice : - Material at site - Re-measured items (quantity variations of BOQ items) - Additional Scope of works / Omitted works. Thanks
@CEPQS
@CEPQS 2 года назад
Thank you brother 🙏. sure, pleasure to do that.
@mdtouseef6940
@mdtouseef6940 2 года назад
@@CEPQS And also sir, How to evaluate these percentage of works? What's the criteria to decide the weightage of works... In usual practice of my experience, I have seen that the QS just sends the BOQ file and asks the Project Manager Or Site In charge to put the percentages against each BOQ item But it would be great to know from you the actual concept of this percentage evaluation. Thanks sir
@CEPQS
@CEPQS 2 года назад
Actually there is more than one way of determining the percentage. But the most famous one is: Let’s assume a building that has 200 apartments. If the plaster work is completed in 100 apartments then completion is 50%. Another example is for wooden doors. They agree some percentages as: 50% shutter , 20% frame 10% installation and 10% touch up, so based on that they determine the total completion % per each door
@CEPQS
@CEPQS 2 года назад
Simplest method in concept is quantity completed / total quantity x 100 %
@nihalahmed7046
@nihalahmed7046 Год назад
Great explanation Sir. I am keep watching your videos. They are very informative and useful
@LifeTone24
@LifeTone24 9 месяцев назад
Very attractive and enthusiastic presentation
@Syed_Mazhar_Ali
@Syed_Mazhar_Ali 10 месяцев назад
Ahmed, I found this video very useful and informative
@sujith25in
@sujith25in 3 месяца назад
Thanks for this informative teaching.
@enricogarado8738
@enricogarado8738 Год назад
i fully understand your explanation sir, thank you for the effort
@CEPQS
@CEPQS Год назад
Thank you for watching and wish you all the best
@keghengsela8681
@keghengsela8681 2 года назад
Thank you for your shearing. latter please make a video how to prepare or explain from Payment certificate. thank you
@CEPQS
@CEPQS 2 года назад
Thank you. Will do 👍
@nrkhan246
@nrkhan246 5 месяцев назад
Thanks Brother your videos are very help ful jizakallah
@vanadjei9698
@vanadjei9698 2 года назад
Excellent delivery...can u make a video about revenue recognition & final account preparation... It's 100% on point
@amanisultanov7450
@amanisultanov7450 10 месяцев назад
Hi, I am taking Construction Economics subject currently and I want to start to learn from scratch with your videos. Do you have those types of videos, let’s say about BOQ, BAFO, basics
@alfredlomotey5935
@alfredlomotey5935 8 месяцев назад
please how where you computing the percentages of the completed works on each stage . was it guessing or a way of calculating . thanks
@duditdudit1805
@duditdudit1805 Год назад
hello sir Ahmed, thank you for sharing this video sir, but i was hoping to see a final tabulated results like what you did in your ''Payment terms explained for construction industry" video, you showed a sample there too, there are some things that was confusing and summarizing the results in a tabulated form would be very helpful too but overall this is really informative and really very helpful, thank you sir.
@CEPQS
@CEPQS Год назад
Thank you for watching and for the request 🙏. I’ll try to fit in the table in one of the upcoming videos. But for the time being please follow the concept explained in this video not in the payment terms. All the best 👍
@iansimakuni5421
@iansimakuni5421 2 года назад
Perfect lecture Sir
@CEPQS
@CEPQS 2 года назад
Thank you brother 😊
@akarqadir
@akarqadir 9 месяцев назад
hello sir why didnt you deducte retention and advance payment frome the upto date work that has been done ? for the first month ...
@mechtrotip5034
@mechtrotip5034 Год назад
Thanks sir for this video I didn't understand why did you subtract 7,565 and add 6,226. Does that not mean you are recovering 20% advance?
@CEPQS
@CEPQS Год назад
The previously paid includes the advance payment and since we deduct 10% from the total work done and we also deduct the provisionally paid, we have to add the remaining advance payment ☺️
@shahad457
@shahad457 6 месяцев назад
In this format the 10% of advance payment is deducted in every month payment application in addition to deduction of total advance payment, which is duplication of deduction. No requirement of 10% advance payment recovery if the total advance payment is deducted and payable advance payment is added.
@jassonjohny1336
@jassonjohny1336 Год назад
Hi ahmed, Not clear why you are adding advance payment remaining. Is there a way we can do this calculation without adding this part?
@markrobinfundimuchangi831
@markrobinfundimuchangi831 9 месяцев назад
Hello Ahmed....what happened of the 864 considered as the remainder of the Advance payment for valuation no 4.....did it just vanish
@chilufyachristopher9804
@chilufyachristopher9804 2 года назад
Well explained. Thank you very much.👍
@CEPQS
@CEPQS 2 года назад
Thank you for watching and for the idea ❤️👍🙏
@olorunyomisalami1970
@olorunyomisalami1970 7 месяцев назад
I need more explanation on the previous payment,since an agreed percentage has been deducted
@ganganathnisansala7769
@ganganathnisansala7769 2 года назад
Why are you deducting two times of advance payment recovery in each bill? First you deduct the 10% of APR from the work done after that you deduct the total advance payment and add the remaining advance payment. Accordingly you deduct the same advance payment recovery for 2 times from each bill know
@CEPQS
@CEPQS 2 года назад
That’s why we add the remaining advance payment 🙂
@Now-Wow
@Now-Wow 8 месяцев назад
Thanks for sharing your knowledge. I have seen all your many videos and almost like all. However I need to ask one thing because It’s confusing when I used the values from your video Terms of Payment and tried to prepare a table with the method shown payment certificate then the answer is not coming same. I hope you understand what I am trying to tell.
@gorgiassokrates
@gorgiassokrates Год назад
Thank you mr. Ahmed for this very informarive video I subscribed and like Can yoh please make a video about whatif the tender price is change by variation order how we can adjust that interim payment aplication format where we will add it on our format just an example and also tell us about price variation
@deliwalazuber
@deliwalazuber Год назад
Thanks for sharing the video, we have the same method. I just wanted to know about the variation amount payments in intrim bills (running bills). As some of the subcontractors / suppliers have different % of advance and progressive payments some times Main contractors are in such a situation where they end up financeing the job and affect the other projects. suggest what is the solution for this and how do you bill this kind of variations in to the intrim billing applications.
@vinothshalabha3200
@vinothshalabha3200 2 года назад
I m awaiting ur more videos.ur explaination is excellent. Can u explain about the BOQ cost load in primerva and resources..I have adoubt in primerva about cost .1.BOQ cost to be typing in primerva Or 2. Separate cost analysis in each activity
@CEPQS
@CEPQS 2 года назад
Thanks Vinoth. Cost loading on program is also something that we can talk about in the near future. Good idea 👍🙏
@schoolfield27
@schoolfield27 8 месяцев назад
Sorry Sir, I am really got so confused. in the 1st payment, the work done of 13,390 AED has been deducted with retention and also to deducted 10% recovery, witch give 10,712 AED. from this stage, is it okay to used 10,712 AED as a Net Pay? I couldn't get it why need to deduct again with Previous and to add Advance payment remaining. and also i try to used the method you have in the other video (Payment terms explained for construction industry) and it result the same as 10,712 AED. i have tried many approached but still its give same result as well. Can you please enlighten me Sir? Thank you
@TitusKimeli-oz7ei
@TitusKimeli-oz7ei 5 месяцев назад
what if there were some materials on site ?
@daviddogbe9097
@daviddogbe9097 2 года назад
THANK YOU AHMED
@CEPQS
@CEPQS 2 года назад
Thank you 😊
@khalidawad9294
@khalidawad9294 2 года назад
In IPC-4 there was remaining amount of advance payment that was supposed to be deducted in the final IPC but that did not happened and instead you show AED 0.00. where is the AED 864 advance payment remaining. ??
@CEPQS
@CEPQS 2 года назад
In the statement at completion you deduct 5% percent only, which means you released 5% retention at completion 🙂👍. This 5% deduction will be released after DLP which is 12 months and when it happens, it means you have paid 100% of contract value. And thank you watching and comment 👍🙏🙂
@jinasbacker7507
@jinasbacker7507 Год назад
very informative... great
@CEPQS
@CEPQS Год назад
Glad you liked it 🙂
@TheKaki1977
@TheKaki1977 Год назад
Thanks a lot Mr Ahmed
@CEPQS
@CEPQS Год назад
Thank you for watching and support 🙏
@mhmdmhmdd2413
@mhmdmhmdd2413 Год назад
i need explain about bond types : performance bond , retention bond..etc. thanks
@dasetha
@dasetha Год назад
Goon job Mr. Ahmed
@CEPQS
@CEPQS Год назад
Thanks a lot for watching and support 👍
@alfredlomotey5935
@alfredlomotey5935 8 месяцев назад
we could not also see the final presentation of last 5% retention
@md.mosharrafimam2587
@md.mosharrafimam2587 Год назад
What are the interview questions for quantity surveyor when he is fresher, mild level, experience in his career level
@irshathabduljamaldeen-vp8np
Where to add the variation and material on site claim in the IP? Please
@mohamedanas5798
@mohamedanas5798 2 года назад
Sir, why do we have to add again the previously paid and advance payment remaining amount? Can you explain?
@CEPQS
@CEPQS 2 года назад
Because we always work on the total work done until the moment of evaluation. So if the total work done until today is 60% and the total work done until last month is 45% it means that 15% has been done this month. But because we work on the total work done then the percentage of retention and recovery are calculated based on the total work done and hence you need to deduct whatever was previously paid. But the problem is that the previously paid is already including deductions from previous months. So to avoid deducting again we add the advance payment remaining 😃. Watch the video again for better clarity 😃👍.
@mohamedanas5798
@mohamedanas5798 2 года назад
@@CEPQS thank you for your response
@TheHamzaysm
@TheHamzaysm 2 года назад
IPC - 01 AED -1,339 IPC - 02 AED -2,987 IPC - 03 AED -4,273 IPC - 04 AED -6,701 IPC - 05 AED -3,782.50 altogether total is - 19,082.50 but u took into account retention amount of IPC 05 only in final account, so what happend other IPC - 01 ~ IPC - 04 RENTION ?
@CEPQS
@CEPQS 2 года назад
Always work on the total work done. Deduct the retention and recover the advance from it. Deduct the previously paid And add the advance payment remaining you get your net 👍
@TheHamzaysm
@TheHamzaysm 2 года назад
@@CEPQS sorry, my question is u deduct some amount in each IPC 1~5. So what about the retention release?
@TheHamzaysm
@TheHamzaysm 2 года назад
can u reply pls
@CEPQS
@CEPQS 2 года назад
@@TheHamzaysm retention is released in the end as elaborated in the video🙂. 5% upon completion and 5% after DLP
@TheHamzaysm
@TheHamzaysm 2 года назад
@@CEPQS yes I understood but u released the retention on final account which u deduct IPC no 5 - 3,782.50. But u didn’t talk about what happened u previously deducted which IPC 01 ~ 04. Kindly explain as much as possible
@dikoydekada503
@dikoydekada503 2 года назад
how do you understand this contract provision regarding recovery of advance payment that says... The advance payment shall be repaid through percentage deductions in Payment Certificates in the following manner: a)deductions shall commence in the Payment Certificate in which the total of all certified interim payments (excluding the advance payment and deductions and repayments of retention) exceeds ten per cent (10%) of the Accepted Contract Amount less Provisional Sums; and b) deductions shall be made at the amortization rate of one quarter (25%) of the amount of each Payment Certificate (excluding the advance payment and deductions and repayments of retention) in the currencies and proportions of the advance payment, until such time as the advance payment has been repaid.
@CEPQS
@CEPQS 2 года назад
Means that they will give you 10% in the beginning, and after the total work done exceeds 10% you will start deducting 25% of each application until the advance payment is fully recovered
@CEPQS
@CEPQS 2 года назад
After that deductions for recovery will stop because advance has been already recovered
@dikoydekada503
@dikoydekada503 2 года назад
thank you. does it mean at early stage there will be zero Advance Payment recovery in the IPCs until such time work exceeds 10%, and at this scheme Advance Payment can be likely recovered before TOC. Is that correct?
@CEPQS
@CEPQS 2 года назад
Yes correct. If you want to know at which amount it will be fully recovered, use this formula 0.10x = 0.25y, where x is the contract value and y is the total work done amount where advance payment will be fully recovered
@CEPQS
@CEPQS 2 года назад
Sorry x is contract value - PS
@sajeeshpulikkal204
@sajeeshpulikkal204 2 года назад
Could u pls share the xl sheet
@fariskhan4513
@fariskhan4513 Год назад
I don't understand about advance recovery. When I add all values you have recovered it comes 15300 aed. But advance which was given at first was 7565 aed. Can you explain this please? Apart from this explanation was awesome.
@CEPQS
@CEPQS Год назад
The recover of advance will not add up to the advance payment value unless the project doesn’t have retention and this will happen only in the end
@CEPQS
@CEPQS Год назад
Don’t confuse yourself. Just follow the mechanism explained 👍
@georgekimutai1298
@georgekimutai1298 Год назад
remember that retention adds up subsequently in every month. we say total retention by end of month 2 and not retention for month 2, such that total retention is seen at month 5. which is 10% of 75560.
@elizabethwasike2752
@elizabethwasike2752 Год назад
Thank you so much Mr. Ahmed for the continuous effort. I am a bit new to the field of Quantity Surveying in terms of experience and your videos have been helpful. I have an inquiry though. I see like the 1339 was deducted twice. It was first deducted to get the 10,712 and then again it is what was deducted from the 10,712 since (10,712-1339) is the same as (10,712-7565+6226) and it equals the 9373. Couldn't it just be deducted once?
@CEPQS
@CEPQS Год назад
Thank you for watching and support and wish you best of luck. The reason there are 2 deductions is that we recover the advance payment and we retain an amount for the executed works. These are 2 different things. To learn more about that you need to watch the video “terms of payment explained” you can find it on the channel. Kind regards 👋🏻
@rosiubaith5786
@rosiubaith5786 Год назад
What about material on site sir ?? We should add in each bill
@CEPQS
@CEPQS Год назад
You should add it in the summary under the total work done 👍
@herbertpinne5466
@herbertpinne5466 Год назад
sorry sir, how did you get 17.70% when most the work item are 100% and 50%?....
@CEPQS
@CEPQS Год назад
It depends on the values of items 👍
@AliHaider-ml4ml
@AliHaider-ml4ml 2 года назад
Can you upload the excel template please
@ericwei8707
@ericwei8707 Год назад
Material on site???
@ahamedhaffan6260
@ahamedhaffan6260 Год назад
can u pls send that pdf?
@sifathsifath443
@sifathsifath443 2 года назад
💓
@CEPQS
@CEPQS 2 года назад
😊
@emrahthengineer
@emrahthengineer Год назад
Hello it is really good video but I did not understand why u omit %20 advance payment I think it should be like I wrote below; IPC.1 During IPC Work Done =13.390 Retention %10 = 1.339 Advance recovery %10=1.339 Net payable amount = 10.712 AED. IPC.2 During IPC Work Done =16.480 Retention %10 = 1.648 Advance recovery %10=1.648 Net payable amount = 13.184 AED. IPC.3 During IPC Work Done =12.860 Retention %10 = 1.286 Advance recovery %10=1.286 Net payable amount = 10.288 AED. IPC.4 During IPC Work Done =24.280 Retention %10 = 2.482 Advance recovery %10=2.482 Net payable amount = 19.424 AED. IPC.5 During IPC Work Done =8.640 Retention to reach up total %5 we need to add 34% of this IPC = 2.918,50 Advance recovery %10=864 Net payable amount = 10.694,50 AED. In Total Paid Amount =10.712+13.184+10.288+19.424+10.694,50 = 64.302,50 AED Total Recovered Advance Payment = 1.339+1.648+1.286+2.452+864 = 7.565 AED Money will be relased after DLP = 75.650-64.302,50-7.565=3.782,50 AED which is 5% of the total amount of contract 75.650 AED
@CEPQS
@CEPQS Год назад
That’s because you work with current. It is always better to work on the total and deduct the previously paid. Deductions are advance and retention and previously paid. But the problem is previously paid includes the advance payment so you can’t deduct the full amount and that’s why we add the advance payment remaining 😁. All the roads lead to Rome. Just make sure you are not paying more than the earned net value 👍
Далее
Modus males sekolah
00:14
Просмотров 10 млн
What Is A Pay Application In Construction?
11:01
Variations In Construction Projects Explained
8:43
Просмотров 19 тыс.
What Are Interim Valuations?  - Quantity Surveying
3:38