Sir very good information. Sir please make video on Direct trip Auto reclosure, how to see reports Will be very helpful for people like us who r new to moder technologies in power system.
Sir, I have a doubt regarding the battery & rack installation. Suppose if the rack is not grounded and the due to some reason there is a leakage path from battery to rack, in that case what would be the voltage between the battery and the metal rack? Also under normal conditions, what would be the voltage between the battery and metal rack?
Thanks for your helpful information.... Plz tell about 24 V DC system trouble shooting.. In case of DCS system or any control panel ground fault..... Problem How to solve it....
Sir assuming 220 v dc ifrom a battery bank , in that case the dc volt is not grounded , so we should not get any volt betwwen ground and poitive / or between ground and negative . How there is potential difference in such cases .?
Hi bro, In our 120 DC charger i am getting fluctuational value... When i am checking with across +& - ve we are getting same 120, but when i am checking positive with ground first one two seconds i will get +80 something and suddenly it will change -ve 30something... Same thing happening in -ve to ground also... What should be the reason
Sir i have a serious question if both are is not coming that time what we do but when I check across both terminal that time voltage is found? Please tell me
Sir. 33kv breaker. Tripping command or closing command not work on control panel switch or scada system so what happened or what I will do for thish situation
Sir ji humre yaha 110dc supply hai substation me positive aur Earth ke saath 34volt aur,nigtave aur Earth ke saath 82volt mil rahi hai,please problem kya ho sakti hai please jankari de 🙏
Sir mere Power House me 24 voltage DC use h.mane positive to ground check kiye to voltage 25 voltage thi.or nagative to ground check kiye to voltage zero thi.kya fault h.
what can be the reasons of failure /burning of trip coil ... do u have any scheme of ABB make Vcb 11 kV ,Type-VD4 ,year-2005 pl make video on trip circuit or trip system operation
1. Somewhere the wires of positive or negative is being earthed. 2. Battery is not healthy and Battery Charger is feeding control supply directly through bus of DCDB. In such case check the Charger output supply and check the battery each cell voltage. Sometimes on load it will be flickering due to unhealthiness of battery of its too old. 3. If wires/NO, NC Contacts of Relays are earthed then it may happen in such situation. *😊Thanks.*
Sir in my station, there are 2 no's of dcdb & each dcdb feeds 4 no's of feeders(total 8 fuses in each dcdb). Output point for dcdb-1 at battery charger is showing +ve to ground as 38v & -ve to ground as 71v. Same situation with output point of dcdb-2 at battery charger. If there is any grounding, I have switched of these 2 MCBs at battery charger(output points of both dcdb). But still I m getting 38v & 71v at MCBs of both dcdb. Plz help
There might be chance of earth fault in DCDB itself or cable coming from charger to DCDB or at battery point. Tou need to check all concerned ckt one by one.
Sair mere ko ap ka ek help chahiye Mai ek jaquar mucury spa install kiya hai usmai problem hai ki RCCB se chalu Kar raha hon to wo trip Marta hai but mcb Mai productchalu ho raha hai
Very good knowledge you are giving please Sir draw a complete circuit diagram including relay, pressure swith, isolator, CT etc interlock for breaker SF6 closing AND TRINPING FUNCTIONS DETAIL
Relay will malfunction ! Relay may be damaged internally. Protection may not operate in such condition due malfunctioning of relays. Relays are costly so it's important to troubleshoot that. Thanks.
It depends upon many factor. What is the size, What is the phasor sequence of both end of the termination point where cable is planned to connect. Simply lay down cable and check the continuity of each phase if cable is 3 core and identity that by marking Red, Yellow and Blue at both end. Continuity should be confirmed of each phase and connect according to already decided phase of termination point.(Like HT/LT Panel end and other end (Like Transformer or Line)