MIVAN Shuttering Procedure I 7 days Slab Cycle I aluminium formwork
In this video, we talk about 7 days slab cycle with mivan shuttering, will discuss procedure with the activities to follow on site each day to achieve 7 days cycle
This video covers all these topics
Day 1
- Grid line work
- Thesi work (fixing of wooden planks )
- Complete vertical column, shear wall and nonstructural wall reinforcement work
Day 2 and 3
- Erection of wall panels, deck panels with all chajjas elevation work
Day 4
- Complete Beam and slab reinforcement work with covering
Day 5
- Complete all Electrical Conduting work and MEP sleeves and cutouts if needed
Day 6
- Complete Gridline checking and supporting work of slab
Day 7
- Complete checking work of RCC, architect, quality and MEP work as per approved drawing and with respecting departments
- Final do Concrete Casting work of slab
and many more...
___________________________________________________
Share, Support & Subscribe👇👇👇
Subscribe: ru-vid.com...
RU-vid: / dndconstruction
Twitter: ConstructionDnd?s=09
Facebook: / dndconstructioncompany
LinkedIn: / dnd-construction-85870...
Instagram: dnd_constru...
Blogger: dndconstructioncompany.blogsp...
Telegram: t.me/dndconstruction
_____________________________________________________
#mivanshuttering #7daysslabcycle #dndconstruction
mivan technology construction
Slab cycle in construction
complete procedure to follow to complete slab in 7 days by mivan technology
____________________________________________________
Disclaimer for my RU-vid channel
The Content in this video is strictly for educational and informational purposes and is not intended to be advice or recommendation of any kind whatsoever.
____________________________________________________
About Channel:
DND Construction: This channel has Technical & Practical construction videos on Civil Engineering from field experience by Narendra Patle.
Email Id for Inquiry: dndconstructioncompany@gmail.com
#dndconstruction
✌Narendra Patle 👷♂️
24 июл 2024