Тёмный

Project Management: Finding the Critical Path, duration and Project Duration | Critical Path Method 

Civil Engineering Exam
Подписаться 16 тыс.
Просмотров 826 тыс.
50% 1

CPM - Critical Path Method||Project Management Technique||Operations Research|| Solved Problem Project Management: Finding the Critical Path, duration and Project Duration | Critical Path Method
construction project management,
project management,
project scheduling,
scheduling techniques,
PERT,
CPM,
Critical path method solved problems,
project crashing,
crashing example problem,
project cash flow,
direct cost,
indirect cost,
time cost trade off,
project management,
project cost crashing,
project resource management,
resource optimization,
cost optimization in project,
cpm live example,

Опубликовано:

 

19 сен 2021

Поделиться:

Ссылка:

Скачать:

Готовим ссылку...

Добавить в:

Мой плейлист
Посмотреть позже
Комментарии : 108   
@radhikapareek2701
@radhikapareek2701 2 года назад
Thank you so much sir ☺️ for such a easy explanation 😊.
@CivilEngineeringExam
@CivilEngineeringExam 2 года назад
Most welcome 😊
@akshaykayapak8209
@akshaykayapak8209 Год назад
nicely easily explained sir..thank you so much
@SharableMail
@SharableMail Месяц назад
very clear easy to understand thank you
@MAHENDRALANJHI-pe8zo
@MAHENDRALANJHI-pe8zo 10 месяцев назад
Thank you sir it is beneficial.
@user-ge6bi3tv9h
@user-ge6bi3tv9h 10 дней назад
❤❤❤❤❤wow thanks 👍 sir, you teach well ❤❤
@addisukorra7322
@addisukorra7322 Год назад
Activity No. Activity description Duration (days) Depends on 1 Site clearance 2 2 Excavation in foundations 6 1 3 Foundations including plinth beam 10 2 4 Column casting up to roof level 10 3 5 Slab and beam of roof 21 4 6 Earth filling and flooring 10 5FS 1 10d 7 Brickwork 10 5FS 1 7d 8 Doors/windows 3 7FF 9 Plastering 10 7SS 1 7d 10 Painting 7 9SS 1 7d 11 Plumbing 7 7FF 1 3d 12 Electrical works 7 11SS 13 Handover 1 10, 11, 12
@a.zgamer3376
@a.zgamer3376 5 месяцев назад
??😅
@g.vofficial7624
@g.vofficial7624 Год назад
Thankyou so much sir good explanation 🙏
@johnkallonyokie
@johnkallonyokie 2 месяца назад
Very clear and understandable thanks
@parameshnaidu5946
@parameshnaidu5946 7 месяцев назад
Easy manner to understand everyone tq so much bro 😊
@amaliaazufa5232
@amaliaazufa5232 Год назад
thanks for the explanations
@adabalanagavenkatavinay1485
Super explanation sir thanku so much
@serbanstere
@serbanstere 2 года назад
One question. Are there any restrictions regarding the intersections between arcs ? Are them allowed in this method ?
@universeisherestudytime8701
@universeisherestudytime8701 4 месяца назад
No intersections shouldn't be practiced ... Yes when u make it for the first time u can intersect but then you can make a neatly drawn network
@029_menaha4
@029_menaha4 9 месяцев назад
Thank you for this video sir
@learnwithb2138
@learnwithb2138 Год назад
Thank you sir 🙏
@shiva_rocky
@shiva_rocky Год назад
Sir good explanation thank u 😊
@madhukarnaidunaidu4852
@madhukarnaidunaidu4852 Год назад
Thank you for the video, useful
@nikhithab4631
@nikhithab4631 Год назад
Easy way and good information sir
@dularakavindu1743
@dularakavindu1743 2 месяца назад
Thank you so much ❤
@ucantbeat2256
@ucantbeat2256 2 года назад
Verry nice
@alindayu
@alindayu Год назад
Very similar to operation management: production routing planning.
@RanjanKumar-vs5ex
@RanjanKumar-vs5ex Год назад
Tomorrow is my project management exam and I'm watching this video for first time 😃
@beckymwale1512
@beckymwale1512 7 месяцев назад
😅
@rohanpansare555
@rohanpansare555 Год назад
So nice ❤
@exploremindtech882
@exploremindtech882 2 года назад
Nice bhai
@safetyadvisorspecialist7272
@safetyadvisorspecialist7272 5 месяцев назад
thank you sir.
@saurabhpandey3535
@saurabhpandey3535 Год назад
Nice video 👌. Well explained.
@CivilEngineeringExam
@CivilEngineeringExam Год назад
Thanks a lot 😊
@md-pind.wala3323
@md-pind.wala3323 2 года назад
Good
@magedrefat1658
@magedrefat1658 Год назад
Very clear
@vinayakbadiger2063
@vinayakbadiger2063 Год назад
Well explained
@bbrakesha4659
@bbrakesha4659 Год назад
Thinks sir
@abunoman1838
@abunoman1838 5 месяцев назад
thanks
@shrinishrinivas9605
@shrinishrinivas9605 Год назад
Tq sir
@vanditapatil5442
@vanditapatil5442 Год назад
How to put numbers in the circles. I wanted explanation for how to number the events correctly
@addisukorra7322
@addisukorra7322 Год назад
Two project activities ‘A’ and ‘B’ (B being dependent on A) have a finish-finish relationship with 8 days ‘lag’. The estimated duration for the activities are 10 days and 15 days, respectively. If activity ‘A’ is scheduled to start on the 12th day from the beginning of project, on which day can you schedule to start activity ‘B’?
@bashirchauhan954
@bashirchauhan954 Год назад
20th
@Chachustp
@Chachustp Год назад
15th ?
@nvennela5602
@nvennela5602 6 месяцев назад
16th?
@cybershrajal
@cybershrajal 27 дней назад
We are computer science student watching this
@shafiqahmed3391
@shafiqahmed3391 Год назад
Hi. Do you do assignments? Related to construction management?
@johnyumbezuze1958
@johnyumbezuze1958 9 месяцев назад
Yes
@danielmbozi3204
@danielmbozi3204 5 месяцев назад
It is so critical
@saravanan02
@saravanan02 5 месяцев назад
Sir CE3302 Important mattum podunga sir pls
@danielkim6672
@danielkim6672 9 месяцев назад
Thank u curry mucnh
@umarrashid82
@umarrashid82 2 года назад
What happened to the slack calculations or float calculations? Arent they necessary to check the criticality and hence find the critical path ?
@CivilEngineeringExam
@CivilEngineeringExam 2 года назад
i'll continue in next video
@mandalapumanikanta3370
@mandalapumanikanta3370 Год назад
​@@CivilEngineeringExam brother can you please tell me tution this subject per one hour daily or every three per a week please brother I very trouble to understand this subject
@mandalapumanikanta3370
@mandalapumanikanta3370 Год назад
Please 🙏🏻 brother
@maingadave4841
@maingadave4841 Год назад
A nice one but am struggling to learn the english
@Sunil_bavoor13
@Sunil_bavoor13 Год назад
thank you sir for explaining this tomarow I have exam PROJECT MANAGEMENT SKIIL (PMS)
@hemanthgowda.
@hemanthgowda. Год назад
Same
@hemanthgowda.
@hemanthgowda. Год назад
Send some important questions
@vengalabhaskar
@vengalabhaskar 2 года назад
is it possible to explain with site activities in a construction site ?
@CivilEngineeringExam
@CivilEngineeringExam 2 года назад
sure
@samuelzvirevo4481
@samuelzvirevo4481 8 дней назад
am confused on activity H,,,,,to put E andJ
@santhosh9121
@santhosh9121 2 месяца назад
😉😉😉
@danielmbozi3204
@danielmbozi3204 5 месяцев назад
But the line you used classify it so short become hard for me to validate the critical path
@shaikhfaiz3450
@shaikhfaiz3450 Год назад
Critical path will be same for everyone or its depends upon different people draw different kind of network draw ? Plz ans me sir or any one plz ?
@CivilEngineeringExam
@CivilEngineeringExam Год назад
same for all
@CrimeMasterGogo900
@CrimeMasterGogo900 Год назад
Sir Path BEIJ Is possible or not and if not than why sir plz reply
@abhimanyudoesanything
@abhimanyudoesanything Год назад
see the arrows its opposite
@Foodvaalebhaiya
@Foodvaalebhaiya Год назад
6:30
@66_priyeshgurjar97
@66_priyeshgurjar97 6 месяцев назад
Sir How long will it take to Complete the Project and Critical Path Duration Is same???
@CivilEngineeringExam
@CivilEngineeringExam 6 месяцев назад
yes
@user-tz1is1cg2h
@user-tz1is1cg2h Год назад
Sir why can't we take B - F - I - H . It will be the the critical path as 4 + 5 + 12 + 22 = 43 , Hence critical path will be 43.
@faithkarimi147
@faithkarimi147 Год назад
Yeah the same question am asking
@_lessthanzero_
@_lessthanzero_ 11 месяцев назад
Check the video again
@rajanbhattarai4229
@rajanbhattarai4229 10 месяцев назад
The time duration of i is 2 not 12
@TechNepal8945
@TechNepal8945 9 месяцев назад
i think this question /answer both are wrong bro there is no activity connected in loop .
@techgarg4250
@techgarg4250 8 месяцев назад
Bhai waha 2 hai not 12 please it again
@neharathod3158
@neharathod3158 Год назад
plz explain proprly. i cant understand
@admanassas1853
@admanassas1853 Месяц назад
This is a PERT chart.....
@sudhanshurohela
@sudhanshurohela 2 года назад
Shortest duration ko select kyu nahi kiya
@muhammadtalha6319
@muhammadtalha6319 Год назад
Mene bhi shortest hi parha hai waise.
@robertfulau4194
@robertfulau4194 2 года назад
.
@bibo5649
@bibo5649 10 месяцев назад
Sir activity D you are confusing us
@Prashant121_
@Prashant121_ Год назад
*20 April 2023 I didn't understand. My exam is in next week*
@omkarkshirsagar3337
@omkarkshirsagar3337 11 месяцев назад
Hechhh (H) 😂👍
@AbhishekTiwari-kv4gq
@AbhishekTiwari-kv4gq Год назад
Sir what is slack time?
@CivilEngineeringExam
@CivilEngineeringExam Год назад
difference between the time allocated to the task and the time it actually takes. flexible time for completion of the project
@AbhishekTiwari-kv4gq
@AbhishekTiwari-kv4gq Год назад
@@CivilEngineeringExam Thanks sir
@Silverwasp72
@Silverwasp72 29 дней назад
B - E - I - J ?
@SanceShaji
@SanceShaji 23 дня назад
Not possible since the arrow is NOT from E -> I instead it is from I->E
@aryamanutkarsh
@aryamanutkarsh Год назад
Tch tch soo confused
@tonnymakokha
@tonnymakokha Год назад
I think the last path is supposed to be B-F-J-H and not B-F-I-H, this is because H is not precedent by I but H is preceded by J, please correct that sir.
@tonnymakokha
@tonnymakokha Год назад
hence the critical path should be 43 and not 34
@140_kenguvabhavesh
@140_kenguvabhavesh 10 месяцев назад
yes,thank you@@tonnymakokha
@annonymousperson8508
@annonymousperson8508 8 месяцев назад
Bro BFJ is complete path then why to add H? I guess it's perfect
@kipngenobrian3473
@kipngenobrian3473 5 месяцев назад
You are right
@Suki4r
@Suki4r 2 месяца назад
This is the most confusing thing for me
@sangrambarla8587
@sangrambarla8587 2 месяца назад
Fr
@Snorlax_Play
@Snorlax_Play 2 месяца назад
Hindi mai bolo sir
@sonamtenzin1255
@sonamtenzin1255 Месяц назад
your answer is wrong for your information
@ivetymutabazi3514
@ivetymutabazi3514 Месяц назад
It's A not Yee 😬😫
@itsarkadey
@itsarkadey Месяц назад
Shut up
@xyz.1234hdgjtvbhh
@xyz.1234hdgjtvbhh Год назад
Its H not hech
@shahneelkhan1442
@shahneelkhan1442 7 месяцев назад
This is wrong
@Rakibul_52
@Rakibul_52 2 месяца назад
Are you From Bangladesh (Diu)
@anishbista645
@anishbista645 2 года назад
time waste mumerical.
@rushnainpadiyar6384
@rushnainpadiyar6384 Год назад
acha
Далее
NETWORK ANALYSIS PART 1
42:41
Просмотров 132 тыс.
Project Management - Network diagram - Example 3
12:08
Просмотров 220 тыс.
How to use PERT Method ? project management
11:29
Просмотров 101 тыс.